PROJECT
65
<< Continued from page 63
1
2
3
1. Circulation pumps.
2. Controls for the new effluent plant.
performs overall monitoring and control
of all systems as well as energy. Sensors
are installed in all systems in the base and
include temperature sensors, pressure
sensors, air and water flow sensors, and
CO 2 and O 2 sensors.
All critical parameters of all systems can
be monitored from the radio room in Block
A. There is also a satellite link to the DEA
(and soon DPW) offices in Cape Town. This
link will enable DPW to monitor the systems
and to provide assistance to the year team
as required.
FINISHING UP
The refurbishment project will be concluded
during the 2018/2019 season. This project
is a fine example of the work undertaken
and successfully concluded by DPW, their
consultant Royal HaskoningDHV, and the
contractor Nolitha.
The final product will ensure the successful
operation of the base for the next 20 years. PA
www.plumbingafrica.co.za
3. The newly completed showers.
LIST OF PROFESSIONALS
Owner / client Department of Public Works
End user Department of Environmental Affairs
Developer Department of Public Works
Project manager Department of Public Works
Consulting
engineers Electrical, mechanical, wet
services, structural, and
civil Contractors Main building, HVAC&R,
wet services, and electrical Nolitha
Gensets CAT
Effluent plant Martin Membrane Systems
Vacuum drainage system Jets
Snow smelter TFD
Pumps Wilo
Controls CAS
BMS Johnson Controls
Product suppliers
Royal HaskoningDHV
November 2018 Volume 24 I Number 9