Plumbing Africa November 2018 | Page 15

13 The Department started with the IRP review and update process in 2015. The review and update process had four milestones and they are: 1. The development of the Input Assumptions; 2. The modelling of a reference case or base case and scenario cases, including analysis of results; 3. The production of balanced scenario; and 4. Policy adjustment taking into account government priorities, policies, and commitments. Following Cabinet approval in November 2016, the Department then published for public consultation on the assumptions. A preliminary base case or reference case was also published, but for information. Key comments received from those consultations were mainly on the consultation process, the projected electricity demand, assumed technology costs, as well as imposing of annual build limits on renewable technologies. • The electricity demand forecast published then was said to be outdated and not aligned to the prevailing economic conditions. The demand forecast was revised accordingly, and a detailed report is available on the website of the Department. • The technology costs used in the plan have also been updated accordingly. The Department spent the period after consultations modelling and analysing the various scenarios and their impact on the energy mix going into the future. Scenarios were analysed in line with the objectives of the IRP, which is to provide an electricity infrastructure plan that aims to ensure security of supply while minimising cost of supply, water usage, and environmental impacts. The scenarios tested include: • The electricity demand scenario, which tested the impact of varying electricity demand projections; • The gas scenario, which tested the sensitivity of the plan to the assumed gas price projections; • The renewables scenario, which tested the impact of removing annual build limits placed on the renewable technologies; and • The emissions constrain scenario, which tested the impact of using a carbon budget approach to constrain emissions from electricity generation compared to an annual ceiling like with peak plateau decline. At a high level, the review of the IRP undertaken indicates the following: • • • • That the pace and scale of new capacity developments needed up to year 2030 must be curtailed compared to what was projected in the IRP 2010. Without a policy intervention, some of the technologies in the IRP 2010, together with new technologies, will not be deployed, as the ‘least cost’ plan contains PV, wind, and gas only; Imposing annual build limits on renewables does not impact the total installed capacity of renewable energy technology for the period up to 2030; and There is significant change in the energy mix post 2030, which is mainly driven by decommissioning of old coal power plants that reach their end of life. While the IRP review considered a period up to year 2050, the approach taken in the draft updated IRP is to adopt a plan for the period ending 2030 and for detailed studies and engagements to be undertaken to better inform the energy mix or path post 2030. • to, with most of the capacity already connected to the grid and the rest to be realised between now and the year 2022. The cost of new generation technologies has significantly come down and this can be seen in the costs of wind and PV, based on the projects procured to date. Jeff Radebe, Minister of Energy. This approach we believe provides the necessary policy certainty while creating the space for all of us to engage in detail on the impending energy transition and the options available to us as South Africa. The engagements will ensure that the transition we undertake is a ‘just transition’ and is inclusive. Some of the studies we have identified already include: • Detailed socio-economic impact analysis of the decommissioning of old coal-fired power plants that would have reached their end of life; • Detailed analysis of gas supply options (international and local) to better understand the technical and financial risks and required mitigations for a renewable energy and gas-dominated electricity generation mix post 2030; • Detailed analysis of the appropriate level of penetration of renewable energy in the South African national grid to better understand the technical risks and mitigations required to ensure that security of supply is maintained during the transition to a low carbon future; and • Detailed technical, cost, and economic benefit analysis of other clean energy technologies, such as clean coal technology, nuclear, and others. The recommended plan uses the least-cost plan as starting point. The least-cost plan being a plan without renewable energy constraints. The following policy adjustments have been incorporated into the recommended plan for the period up to 2030: • The retention of annual build limits for the period up to 2030. This provides for consistent and sustained roll-out of renewable energy for the period. • The inclusion of 1 000MW of coal-to-power in 2023–2024, based on two already procured and announced projects. • The inclusion of 2 500MW of hydropower in 2030 "Increasing electricity prices have also made substitutes such as LP gas a viable alternative for cooking and heating." Continued on page 15 >> www.plumbingafrica.co.za November 2018 Volume 24 I Number 9