Another issue here was the fact that some of the
boreholes had substantial water yields and diverting
the water from the drilling area was challenging.
There was also no Eskom electricity on site but luckily,
this could be overcome with the use of a generator.
“There were no serious challenges, but planning
was important,” explains Holden. “The project was
simplified thanks to a great deal of assistance by the
main construction contractor.” PA
LIST OF PROFESSIONALS
Project manager John Wicks CIR Construction
Contractors Main building CIR Construction
HVAC and wet services Reliance Eco
Geothermal drilling, testing, and installation of ground-loop system Aqua Earth
Product suppliers Heat pump-chiller; FCUs, electronic thermostats, chilled water buffer tank,
FCU valves, and actuators
AERSA
Hot water buffer tanks, gas boiler, distribution manifolds, high temperature
and mixing group-sets for all hydronic systems, three-way diversion valves,
PLC control system, and HMI Valsir Uneeq
Alpin Easy Flat plate solar collectors Solar Energy
VS Giga variable speed pumps for FCU supply Wilo