Plumbing Africa August 2020 August 2020 | Page 30

28 PROJECT the hot water design, piping installation, how quickly the boilers heat up and how rapidly they cool, and the water coming out the tap – LEED confirms the design matches the energy and water efficiency requirements of the client.” Challenges with design Campbell explains that LEED was chosen over other international green systems for a number of reasons, but primarily because LEED audits, does physical checks on everything and follows through on its system before issuing its rating. “They have a process which verifies each facility as it is complete that it conforms to their requirements, thereby giving the client reassurance – because otherwise this building is a big project to track.” The Grundfos pumps are on back-up generator power, so that the building will always have water. The extent of ground water was a challenge relative to the site, says Colin, though that primarily affected the civil engineers “who sorted that out” says Griffiths. These were not especially challenging, they say, but simply the parameters of the design. Bulk earthworks for the project started in August 2017. The development was scheduled for completion in the first quarter of 2020. Deloitte began operating from its new South African base from April 2020. The real challenge was the tight time frames demanded by the client, due to financial constraints and the need to start getting a return on investment in the form of rent. The entire construction phase has been achieved in virtually a single year. The wet services engineers worked closely with the architects as to the specifications of the wet services system, which the architect then made provision for in the drawings. “We give them the parameters of what we need in terms of space and head room and they then try work around that.” Although there is also a combination of rainwater harvesting and borehole water, the heart of the plumbing systems at the Deloitte building is water supplied from the municipal mains. irrigation with 100% harvested rain/sub-soil drainage water. Notwithstanding the extent of the property, Campbell explains that the pump is relatively small as the irrigation works on a circuit system and irrigates by the hydroponic drip system. With the addition of a special flow limitation system the faucets by Hansgrohe/Duravit reduce water consumption by up to 60%. The Duravit urinal flush systems have flush actuator plates set at only one litre a flush. These flow capacities are dictated by the LEED rating system. Campbell says that on some jobs, the design provides for many more hand driers in toilet blocks to encourage greater hygiene. The rainwater harvesting system was design by DG Consulting Engineers. Gayle Griffiths, Wat-Sol Design Technology, design and quality control manager, says that the primary objective governing the design was conformance to the LEED water efficiency requirements. “It governed the entire design as it what the client (Atterbury and Attacq) wanted. It governed The installation of the heat pumps in the main plant room in the first and second basements, supplying the kitchens was undertaken by Jazzman Plumbing, (with TekniHeat units – large boilers and heat pumps), and SA Heat Pumps (two smaller boilers and heat pump) on the roof to supply the sixth floor only. Griffiths says, “We would generally install heat pumps in any case due to the requirements of SANS 10400-XA energy efficiency regulations, but LEED does not permit anything but alternative energy sources. Heat pumps were selected primarily because of the space limitations – as there is not enough roof space for solar panels. The heat pumps – there are three heat pump plants – are located on two different basements and a third on the roof, in the case of the basements, they occupy a couple of parking bays against the wall with sufficient ventilation. All three are directly in line (above or below) with the building’s kitchens so as to limit the pipe run (even though the pipes are well cladded). The heat pumps were set to a certain temperature to meet LEED’s energy efficiency requirements. “It is all very tight – you have to fight for this space,” says Dowie. “We used the Valsir piping system with the joints welded. It also has a Sensus water meter (specially stipulated in the specs) which constantly monitors the water flow so the owners can measure the water consumption throughout the building. “Given the cost of water, it’s good practice.” www.plumbingafrica.co.za @plumbingonline @plumbingonline @PlumbingAfricaOnline August 2020 Volume 26 I Number 06