Plant Equipment and Hire February 2020 | Page 17

ON SITE support. Mesh is applied to the sides of the shaft and depending on the shaft diameter, a thick layer of shotcrete. The platform features a shotcreting system which applies a layer of shotcrete as the machine descends further down the shaft. Kibbles are used to hoist the concrete used in the shotcrete mix up and down the shaft. Jordaan says they will need to hook and unhook about four or five different kibbles depending on whether they move people, concrete, equipment or excavated rock material. “Obviously there is a lot of intelligence running down the main stage into the machine, so there needs to be a proper handling system for all the hoses, hydraulics, electrics and communication cables,” explains Jordaan. The stage platform carries all the support equipment, including, amongst others, compressors, high tension power cables, transformers, agitator tanks, vacuum pumps and a hydraulic deck. The hydraulic deck is designed in such a way that it can be configured for a lower kilowatt usage and for a range of different diameters. Advancing into solid rock Above the stage is the lifting phase which is designed and built to retrieve the machine once the shaft has reached the bottom, which could be more than 2km deep. The sheer weight of the machine makes it unsafe to hoist it to the top, and therefore the boring machine, support stage and equipment needs to be dismantled and lifted out of the shaft in separate pieces. A sturdy headgear which is easy to remove will be used to hoist the machine back to surface. The entire system at the Master Drilling site was run off a 400 Volt generator with a transformer that converts the power to 525 Volts. When the group visited the test site, the machine was advancing at a rate of more than 500mm per hour, however, Jordaan says they are hoping to optimise and improve the penetration rate to more than 650mm an hour. He further explains that the gravel-sized fragments of the rock cuttings indicate the efficiency of the machine. “Cuttings should not be fine-grained sand. Big fragments are a good indication that the cutter head is operating quite efficiently. Banana shaped chips, which we normally get with our Tunnel Borer, is a good sign,” says Jordaan. In a rapidly changing world, where mechanisation is no longer just blue sky thinking, the shaft borer is leading the pack into new frontiers. Using the machine to sink a shaft will not only be a lot faster than conventional methods, it will also be safer, and it will reduce the overall costs significantly. Jordaan says that only 20% of the personnel needed on a conventional sink are deployed when drilling with the shaft borer. Moreover, only 50% of the power is needed. The estimated cost of the entire system will be in the region of R500-million. Although there has not been interest from prospective buyers yet, Jordaan explains that they will be targeting certain regions in the world where there has been an increase in mining activity, Russia and Kazakhstan being the most prominent. “Through our global distribution and business network we are aware of where shafts will be sunk, the geology in those areas and how they will be constructed. At the same time, we are still in the process of testing the machine and we’ve invited several groups and potential clients from around the world to come and see what we are doing,” says Jordaan. He adds that once an order has been received, the system could be up and running within a about 12 months. When the group left site, the machine was still grinding away steadily, leaving behind stockpiles of norite fragments in the hot summer sun. Other than the growing piles of rock, a massive black steel frame, a generator and vacuum system, there was absolutely no sign that underneath our feet a perfect shaft was being sunk, with almost no effort, no blast, no noise, no dust and with a workforce of only six – an extraordinary feat. The drilling team on site, from left: Klint Somerset (Electrician), Pedro Mucale (Assistant), Nicol Goodwin (Project Engineer), Walter Tshabalala (Fitter), Lukas Muller (Site Manager), Gordon Brandon (Fitter). www.equipmentandhire.co.za JANUARY/FEBRUARY 2020 15