Plant Equipment and Hire August 2019 | Page 23

here in South Africa,” he says. “The imported components are typically laid down and stored in the port until the site is ready to receive these components. Once the wind farm site is ready, these components are loaded onto abnormal load vehicles at the port for road transport to site. Upon arrival at site, the components are offloaded on the individual WGT crane pads for installation; this is done using the 750t LG 1750 as the main crane.” The weight of the tower sections varies and could be up to 81t per section. Two cranes are required to lift the sections from a horizontal to a vertical position. The main crane then holds the section in place while it is being bolted to the foundation or lower section. The componentry for the power generating function of the turbine also comprise substantial weights. “With the tower in place, the lifting and placement of the nacelle with generator, drive train and gearbox installed – weighing up to 97t – follows. In some instances, the generator, gearbox and drivetrain are installed separately due to the excessive heights at which these components need to be installed,” he says. “The rotor consisting of the hub and blades completes the mechanical installation. The hub itself could weigh up to 30t while each of the three blades could be as much as 15t.” Grotius says two very different concepts are being used when it comes to the installation of the rotor and Johnson Renew’s lifting expertise covers both installation concepts. Some OEMs require the hub and blades to be assembled on the ground and lifted as a unit which is then attached at height to the nacelle. Others require the installation of the hub as a single unit with the blades installed separately at height. “Each option has its own complexities,” says Grotius. “For www.equipmentandhire.co.za installing blades separately, for instance, a special tool is required to clamp the blade when lifting so it can be aligned to the hub and secured.” To lift and install an assembled rotor, on the other hand, there is the combined 75t weight to consider as well as the length of the individual blades that could be as much as 67 metres. This assembly needs to be lifted from a horizontal position using two cranes, and carefully manoeuvred using guy-lines from the ground to keep the blades clear of the boom of the crane and the installed tower sections and to align it for final installation. “Designed with large surface areas relative to their weight, the blades can be quite tricky to lift and place, especially as there are usually intermittent periods of sufficiently low wind speeds during which these lifts can be carried out,” he says. “Success is all about the engineering and planning of these lifts. We select cranes of optimal capacity, and apply the highest levels of experience and expertise, from computer modellers through to crane operators to ensure the safest possible execution of these lifts.” It is also vital to calculate in advance the maximum wind speed that the lift can accommodate, and then to monitor the wind on site closely to ensure that work is conducted within the prescribed limits. “The challenge is obviously the pressure of keeping to the project schedule, which usually requires installing up to two turbines a week,” says Grotius. “We therefore have to be flexible with regard to the timing of the lifts and the affect this has on our working hours. If the wind speeds are too high during the day, we may have to work through the night when the wind speed drops to acceptable levels for safe lifting and by doing this we keep the project on track.” Renew PRODUCT FOCUS Installation underway at a wind farm using a 1 200t hydraulic crawler crane in combination with a 100t crane. LIEBHERR LG 1750 Among Johnson Renew’s fleet of mobile cranes – the largest in Africa – are three specialised 750t Liebherr LG 1750 lattice boom mobile cranes, ideal for wind farm work. Mounted on a wheeled carrier, these mobile cranes can move along a standard road between wind turbines. This eliminates the need to construct excessively wide and expensive roads that are required for the large crawler cranes. The LG 1750 can also rapidly relocate between installation pads, saving time and costs and adding value to the project. AUGUST 2019 21