Palm Beach Undergrounding Master Plan COMPLETE MP Online-v5 | Page 205

Town of Palm Beach Master Planning Engineer’s Conceptual Opinion of Probable Cost for Undergrounding Phase 7 South Item No. Description Amount $1,060,000 1 FPL Overhead to Underground Conversion 2 AT&T Overhead to Underground Conversion $370,000 3 Comcast Overhead to Underground Conversion $250,000 4 Roadway and Private Property Restoration $960,000 5 FPL Direct Costs 6 AT&T Direct Costs $270,000 7 Comcast Direct Costs $120,000 8 FPL Service Conduit (Private Property) $290,000 9 Engineering/Permitting/Surveying $380,000 10 Construction Administration $270,000 11 Legal Fees Credits FPL Credit – 25% GAF Waiver $110,000 12 $1,120,000 ($600,000) Subtotal Estimate – Today’s Dollars $4,600,000 Subtotal Estimate – Considering Inflation $5,500,000 Contingency $500,000 Total = $6,000,000 TOWN-WIDE UNDERGROUNDING OF UTILITIES PROGRAM MASTER PLAN DOCUMENT OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COSTS | 179