Palm Beach Undergrounding Master Plan COMPLETE MP Online-v5 | Page 203

Town of Palm Beach Master Planning Engineer’s Conceptual Opinion of Probable Cost for Undergrounding Phase 6 South Item No. Description Amount $2,250,000 1 FPL Overhead to Underground Conversion 2 AT&T Overhead to Underground Conversion $740,000 3 Comcast Overhead to Underground Conversion $480,000 4 Roadway and Private Property Restoration $1,610,000 5 FPL Direct Costs $3,130,000 6 AT&T Direct Costs $360,000 7 Comcast Direct Costs $160,000 8 FPL Service Conduit (Private Property) $390,000 9 Engineering/Permitting/Surveying $770,000 10 Construction Administration $290,000 11 Legal Fees Credits FPL Credit – 25% GAF Waiver $230,000 12 ($1,310,000) Subtotal Estimate – Today’s Dollars $9,100,000 Subtotal Estimate – Considering Inflation $10,500,000 Contingency $970,000 Total = $11,470,000 TOWN-WIDE UNDERGROUNDING OF UTILITIES PROGRAM MASTER PLAN DOCUMENT OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COSTS | 177