Palm Beach Undergrounding Master Plan COMPLETE MP Online-v4 | Page 207

12.9 Cost Reduction Opportunities The opinion of probable construction cost was prepared based on the understood goals and objectives of the program which include conversion of all overhead utilities to an underground location within the Town municipal limits. At the request of the UUTF, this master planning effort explored several cost reduction opportunities that could be considered by the Town. However, these opportunities may require the goals and objectives of the program be altered, variances from the Town Code of Ordinance requirements be issued, utility owner design standards changed, or offsetting revenue and/or grant funding be applied to the program. A summary of such options is presented below: 12.9.1 Alternative Program Goals and Objectives The opinion of probable construction cost could be reduced if the amount of overhead utilities to be converted to an underground location was reduced. This could be accomplished in a variety of ways. y y Phase areas could be selected to not be converted underground y y Feeder Infrastructure along the major arterial roads could be converted underground with the radial infrastructure largely remaining in their current aerial locations TOWN-WIDE UNDERGROUNDING OF UTILITIES PROGRAM MASTER PLAN DOCUMENT y y Feeder Infrastructure could be hardened in accordance with FPL’s hardening plan with only the radial infrastructure being converted to an underground location y y Various combinations of the above three concepts While the above concepts could significantly reduce program costs, they do not accomplish the original vision of the Town to convert all overhead utilities to an underground location. There are also other ramifications that need to be considered when reducing the scope of the program: y y Depending on the level of scope reduction, the GAF Waiver may no longer apply unless FPL Tariff minimums are met. For example, in the instance where only feeder infrastructure along main arterial roads were to be converted underground, if the affected laterals were not converted in their entirety, the GAF Waiver would no longer apply according to the FPL Tariff. y y The aesthetics, reliability, and safety benefits of a partially converted system would be less than the benefits of a totally converted system. This may also complicate the assessment methodology. 12.9.2 Town Code of Ordinance Requirements The opinion of probable construction cost could be reduced if the Town’s Code of Ordinances did not include a requirement that the above ground equipment to be installed with the undergrounding program be screened from view from the public right of way. This equipment screening requirement adds over $500,000 to the program budget but cannot be eliminated without a variance from the Code. 12.9.3 Utility Owner Design Standards The opinion of probable construction cost could be reduced if FPL, AT&T, and Comcast altered their design standards for the project. AT&T and Comcast have already offered conduit standard revisions exclusively for this program which has reduced the opinion of program cost. There may be other changes that could be made by the utility owners to further reduce costs. However, requests for further design standard changes must be approached cautiously. Only FPL, AT&T, and Comcast can make decisions regarding how their systems are to be designed and installed. Their system standards have been developed over many years of operational experience and efficiency improvements. There are also elements of their design standards that enhance the system reliability and removal or alternation of those elements could create a system that is less reliable, prone to operational problems, and difficult to maintain. The Town can continue to explore these opportunities with the utility owners with the understanding that opportunities may be limited and the utility owners may be unwilling to modify their standards any further. 12.9.4 Offsetting Revenues, Credits, and/or Grant Funding The opinion of probable construction cost could be offset by a variety offsetting revenues, credits, or grant funding opportunities. This would ultimately result in a lower net cost realized by the Town for the program. These opportunities include the following: y y Additional credits or financial contribution from the utility owners. There is a benefit that each utility owner realizes in avoided storm recovery efforts after an underground conversion is complete. Currently, only FPL offers a credit (GAF Waiver) for this benefit. The Town should continue to explore ways the utility owners can participate in offsetting the cost of the program based on the benefits they will receive. This can take on the form of enhanced credits, no cost system betterments, etc. y y Broadband Infrastructure Revenue. The Town could decide to use the program as an opportunity to assist in the installation of another communications service provider to OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COSTS | 181