Palm Beach Undergrounding Master Plan COMPLETE MP Online-v4 | Page 191

12.8 Opinion of Probable Cost Summary Opinions of Probable Construction Cost by project phase are provided below. A summary of total project costs, including contingency and inflation, is provided below. Town of Palm Beach Overall Program Opinion of Cost Summary – March 2017 Item No. Updated Opinion of Probable Cost Description Town of Palm Beach Master Planning Engineer’s Conceptual Opinion of Probable Cost for Undergrounding Individual Phase Opinion of Probable Cost Summary Item No. Phase Phase Cost– Phase Cost– Today’s Dollars Considering Inflation Contingency Total 1 Utility Conversion Costs – FPL $43,900,000 1 Phase 1 North $4,500,000 $4,500,000 $400,000 $4,900,000 2 FPL Credit – 25% GAF Waiver ($11,200,000) 2 Phase 1 South $7,120,000 $7,120,000 $600,000 $7,720,000 3 FPL Service Conduit (Private Property) $4,150,000 3 Phase 2 North $3,800,000 $3,900,000 $350,000 $4,250,000 4 Utility Conversions Costs – AT&T and Comcast $15,960,000 4 Phase 2 South $4,400,000 $4,500,000 $420,000 $4,920,000 5 Roadway and Private Property Restoration $15,100,000 5 Phase 3 North $3,500,000 $3,800,000 $340,000 $4,140,000 6 Engineering/Permitting/Surveying $7,050,000 6 Phase 3 South $5,800,000 $6,200,000 $570,000 $6,770,000 7 Construction Administration $3,970,000 7 Phase 4 North $4,300,000 $4,700,000 $430,000 $5,130,000 8 Legal Fees $2,000,000 8 Phase 4 South $4,400,000 $4,800,000 $440,000 $5,240,000 9 Public Outreach $570,000 9 Phase 5 North $5,400,000 $6,000,000 $550,000 $6,550,000 Subtotal Project Costs $81,500,000 10 Phase 5 South $6,200,000 $6,900,000 $640,000 $7,540,000 Contingency $8,140,000 11 Phase 6 North $4,300,000 $4,900,000 $450,000 $5,350,000 Inflation $8,940,000 12 Phase 6 South $9,100,000 $10,500,000 $970,000 $11,470,000 Total Project Costs $98,600,000 13 Phase 7 North $4,400,000 $5,250,000 $480,000 $5,730,000 14 Phase 7 South $4,600,000 $5,500,000 $500,000 $6,000,000 15 Phase 8 $9,100,000 $11,300,000 $1,000,000 $12,300,000 16 Public Outreach $570,000 $570,000 – $570,000 TOWN-WIDE UNDERGROUNDING OF UTILITIES PROGRAM MASTER PLAN DOCUMENT OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COSTS | 165