Palm Beach Undergrounding Master Plan COMPLETE MP Online-v4 | Page 174

and GMP development needed to prepare for an early May construction start. Construction Phase Schedule Considerations y y Bidding of the major trades should occur at the beginning of each year to allow construction to commence by May y y “Heavy” construction activities, such as underground infrastructure work and conduit installation are desired to be constructed in the summer months when traffic volumes are lowest y y Year-round construction activities have been approved by the Town Council for the undergrounding program y y “Heavy” construction activities should begin in early May and be completed by Thanksgiving to the greatest extent practical y y To minimize traffic impacts, “heavy” construction impacts will not be allowed to occur in adjacent phases at the same time y y Cable and equipment installation activities may overlap the duration of backbone conduit installation within a phase y y Feeder switch over to the underground system would occur in the cooler months when electrical demand is low which reduces the complexity of the process and associated costs 150 | CHAPTER ELEVEN y y Conversion of individual electric and communications services will follow the energization of the new underground system y y Overhead wire and pole removal cannot begin until all services are converted to the new underground system Schedule Durations The durations of significant activities that occur within each project phase were developed based on information gathered from a variety of sources. Design durations are largely based on Kimley-Horn’s experience with similar projects and through schedule discussions with FPL, AT&T, and Comcast. Construction activity durations were based on general rates of production that area contractors with undergrounding expertise felt were reasonable for scope of work involved. Combining these production rates with mass quantities for the project developed as a part of the opinion of cost development yielded significant activity durations and were then incorporated into the overall schedule. Appropriate schedule contingencies were also applied to account for normal weather impacts, potential geological challenges (rock), and unforeseen conditions. TOWN OF PALM BEACH