Materials and services |
115,203 |
113,761 |
117,250 |
148,900 |
139,210 |
One-off initiatives ( operating projects ) |
40,728 |
897 |
38,000 |
18,000 |
15,300 |
Capital expenditure Asset renewal |
55,463 |
30,746 |
- |
- |
- |
New works |
- |
40,847 |
118,327 |
30,000 |
30,000 |
Upgrade works |
- |
- |
- |
33,000 |
33,000 |
Total capital expenditure |
$ 55,463 |
$ 71,593 |
$ 118,327 |
$ 63,000 |
$ 63,000 |
* Includes ground maintenance . |
1.6a |
Operating |
Replace shoring and ground cover – required |
Regional |
to be up to standard for Workplace Health |
$ 18,000 |
||
and Safety . |
|||
1.6b |
New |
Construction of a brick wall at the Mitchell |
Mitchell |
Cemetery for memorial and placement of |
$ 30,000 |
||
ashes |
|||
u1.6a |
Upgrade |
Water System upgrade – Auto Sprinkler System ( Tank & Solar Powered Pressure Pump ) ( Wallumbilla Town Improvement Group |
Wallumbilla |
request - to allow stage 2 of the Wallumbilla |
$ 33,000 |
||
Cemetery water system upgrade and facilitate | |||
the installation of a pop-up sprinkler system in | |||
the lawn cemetery ) | |||
TOTAL PROJECTS |
$ 81,000 |