2. In setting up a kanban control system you need to determine the
number of kanban card sets needed. If the expected demand during lead
time is 25 per hour, the safety stock is 20 percent of the demand during
lead time, the container size is 5, and the lead time to replenish an order
is 5 hours, what the number of kanban card sets is needed?
27
20
5
30
3. Which of the following is a multifactor measure of productivity?
Output/(Labor + Capital + Energy)
Output/All resources used
Output/(Materials)
Output/Inputs
4. Which of the following is an alternative possible service encounter
included in the service-system design matrix?
Internet
Automated teller (ATM)
Face-to-face distance
Questionnaire response
5. In development of an operations and supply chain strategy, which of
the following may be an important product-specific criteria to consider?
Learning curve
Supplier after-sale support
Production lot size
Focus
6. Which of the following is one of Dr. Eli Goldratt's rules of production
scheduling for optimized production technology?
An hour lost at a bottleneck saves an hour for the entire system
Do not allow bottlenecks to govern the flow of the line
Utilization and activation of a resource are not the same
Balance the capacities, not the flows
7. You have just been assigned to oversee a series of projects. Functional
areas will loan you personnel for each project, and separate project