Onshore Energy Conference — Dubai Onshore Energy Conference — Dubai 02 | Page 36

CURRENT THOUGHT HV UNDERGROUND CABLE INSTALLATIONS W e see HV underground cable claims either as first party claims as a result of damage caused during erection or installation or as TPPD claims. This note concerns the former. HV Cables are generally laid in about 500 metre spans between substations with joint bays making the connections to cover the distance. The joint bay is usually a buried concrete box enclosure. A 400kV cable with a single conductor will weigh around 26 tons net of its drum, ie about 52kg/metre. HV cable values are very high not least because a significant part of the weight is made up of the copper conductor. When damage occurs, as often as not, it is located somewhere in a span but distant from an existing joint bay. Unless there are local ground conditions which prevent it, it should generally be possible to consider jointing the cable at the damage location using a single straight through joint. However, it is invariably the case that the construction contract does not permit the insertion 36 By John Kidd of an extra joint in a span that was not designed to be there in the first place. As a result the Contractor has to replace the complete span from joint bay to joint bay. The considerable cost involved in that replacement becomes the Contractor’s claim against the CAR/EAR policy. The question Adjusters are faced with in such circumstances is whether Insurers should pay for the replacement span or only for the notional joint repair cost? Leaving aside the contractual obligations, the Contractor will generally make the case that an extra joint is a weak point to be avoided. I am not particularly impressed with that argument as in, for example, a 5 km route there would already be 10 joints and in a 10 km route 20 joints. I am not convinced that one extra joint in the route makes any difference. I have yet to see a claim for a failed joint, so I think the premise that a joint is a weak point may be more illusory than real in practise. Another aspect that is difficult to reconcile is that we know that once a cable route is taken over by the utility if,