One USQ Connectivity & Experience Projects - Activity Report June 2016 | Page 5
One USQ Connectivity Project
Learning and Teaching Space Upgrades
Toowoomba T and Z block teaching space upgrades have been
completed as part of the One USQ Connectivity Project (1UCP).
1UCP in consultation with key stakeholders has developed a new
teaching space standard for upgrading existing USQ L&T spaces
to significantly transform them to become a showcase for flexible,
technology enabled teaching at USQ.
What does this mean?
Troy Downs
Manager
Unified Communication Project
The following Toowoomba spaces have been completed and as a
result are flexible didactic teaching and exam spaces.
•
•
T121, T125, T124, T120, T119, and T118
Z125, Z129, Z312, and Z313
The following Toowoomba spaces have been completed and as a
result are collaborative Pod and exam spaces.
•
T110, T111, T112, T113, and T122
Next Steps
Throughout 2016 and prior to the start of Semester 1 2017, 1UCP
will be working on the next phase of teaching space upgrades. This
will be the tutorial and lecture theatre spaces at Springfield Building
A, including the Auditorium.
Unified Communications
Throughout 2016 1UCP has been working with key stakeholders and
trialling new unified communication products to help identify those
that will form part of the Video Conference as a Service offering.
Video Conferencing as a Service
1UCP is still developing the products that will make up this service,
with a particular focus on providing a consistent approach to both
using and supporting the final offering.