A SWMS must include the following information :
− identify the high-risk construction work activities to be carried out on-site − the hazards and risks to health and safety arising from these activities − the measures to be implemented to control the risks , and − how the control measures are to be implemented , monitored and reviewed .
Complying with a SWMS
WHS Regulation clause 300 Compliance with safe work method statement
If high risk construction work is not carried out in accordance with the SWMS for the work , the PCBU must ensure that the work is :
- stopped immediately or as soon as it is safe to do so , and - resumed only in accordance with the statement .
More information about a SWMS for high risk construction work and a SWMS template can be found in the Code of Practice : Construction work .