Table. 1 : Public Hearing Time Line
No. J-II 0 15/30/2004-IA.I1 (M) guidelines about exemption in
PH for expansion of Coal Mining Projects (one time – 25%).
29.08.13 No. J-11013/19/2012-IA.II(I)- on Storing the records relating to
processing of cases for Environment Clearance and Forest
Clearance electronically.
07.01.14 No. J-II 0 15/30/2004-IA.I1 (M) on guidelines about exemption
in PH for expansion of Coal Mining Projects (one time – 50%).
16-05-14 No.]-11013/36/2014-IA-I on exemption from Public
Consultation for the projects/activities located within the
Industrial Estates/ Parks.
30.05.14 Project already availed 25% clause can avail under 50% clause
also.
50% clause extended production capacity exceeding 16 MTPA
(additional production up to 5 MTPA).
28.07.14
22.08.14
F.No. J-11013 l4L12006-IA-II (I) (part) : The SPCBs shall ensure
that the PH is conducted within the timeline of 45 days as
prescribed in the EIA (2006) & within the validity period of the
TORs, and that no PH is held after the validity period, of TORs is
over.
Special Volume 1, October 2015
54