This will also jolt down the PH timeline. Altogether PH for 121 project have been analysed covering 16 different state of India. An issue tree was framed. Analysis for brown as well as green field projects, UG as well as opencast project, mining and non-mining projects, coal mining projects amongst mining projects, where data for PH collected from different sources and personal interventions.Public Hearing provides a legal space for people of an area to come face-to-face with the project proponent and the government and express their concerns. Various Office memorandum, circulars and amendments to it have issued for the PH process by Ministry of Environment and forest & Climate change, Government of India from time to time. The time line can be observed at table. 1. 10.04.97 13.06.02 Table. 1 : Public Hearing Time Line The process of environmental public hearing (EPH) was introduced in the environmental clearance process. The SPCBs were entrusted to conduct public hearing to get the views and concerns of the affected community and interested parties for the proposed project. It was also entrusted with forming an EPH committee to ensure fair representation in the public hearing process. It exempted pipeline and highway projects from preparing the EIA report, but these projects would have to conduct public hearings in all the districts through which the pipeline or highway passes. Special Volume 1, October 2015 49