Mining Mirror March 2019 | Page 17

Mine excursion sourced for the project, over and above the 103 000m3 of aggregate used for the road layer works. These quantities demonstrate the sheer extent of the construction works that were completed in such a short period, and Visagie says that Jodan Construction’s strong team on site also played a huge part in helping the professional team meet this onerous deadline by consistently maintaining the required high-quality levels. This is in addition to the significant resources that the contractor deployed to the project to keep works progressing according to schedule. For example, more than 70 tipper trucks were on site to transport construction material to the various work faces — an extensive logistical undertaking that required close and careful coordination. Meetings were held almost daily between representatives of the contracting, engineering, and Exxaro project teams to regularly assess progress made and to anticipate and quickly solve challenges as and when they arose. Certainly, the hands-on approach adopted by the client and its willingness to assist in solving complications, and excellent team dynamics between all representatives of the professional team as well as the contractor, also played a large part in the successful outcome. Innovative solutions for complex challenges One of Visagie’s critical functions on site was to provide technical advice to the professional team, and he is very proud of the extent of innovation that was deployed on this project to solve many challenges. This includes working in a wetland through which the new provincial and district roads traversed. A novel solution was devised to stabilise the bases for the 14 large, 2.4m × 3m stormwater structures that were installed in this marshy terrain with rock grid, bidim, rockfill, and 19mm and 6.4mm aggregate. Another example of innovative thinking was the use of impact compaction rollers on as much as 80% of the road distances to accelerate the treatment of large areas located in commercial maize farmlands. Impact rolling has the added benefit of obtaining much better levels of compaction at depth. Better compaction of the substrata creates a stable platform to construct a surfaced pavement structure highly resistant to permanent deformation. Notably, the private road features a 16mm micro surfacing, Ralumac. Ralumac is a rapid-setting cationic modified rubber bitumen slurry AC-E1 and known industry-wide as a surfacing alternative that facilitates fast construction. The resulting surfacing is highly durable and resistant to permanent deformation, like rutting and shoving. “It has been used extensively in the country on public-sector road construction projects such as those by the City www.miningmirror.co.za Marshy area filled with rockfill using end tipping. of Tshwane Roads and Stormwater Department. This was the ideal opportunity to introduce the client to a more affordable and longer-lasting surfacing product, the performance of which will be monitored as part of a trial period. The service life is largely dependent on the aggregate type used, but will likely last in excess of 10 years, provided good-quality aggregates were sourced,” Visagie says. One of the challenges on this component of the project was coordinating construction activities on the private road with the extensive haulage operations of Exxaro coal mine. The haul road serves many large rigid dump trucks. A semi-automated traffic and access control boomgate system was implemented for the level crossing with the public road. The road comprises a 150mm thick base course, 200mm sub-base layer and two selected layers. The contractor deployed a state-of-the-art road recycler for stabilisation to provide a consistently homogenous mix, with cement bags unpacked and squeegeed by hand to assist in creating jobs via labour-intensive construction practices, despite the fast pace of construction required. The provincial corridor caters to high traffic volumes and this includes the many heavy commercial vehicles that use the road and abnormal loads that are transported to and from mines and other industries in the area. To maintain high road safety levels, the bypasses along this route were built to high pavement standards and illuminated with solar studs and mobile high mast lights, while extensive signage was installed on both sides of the road to alert traffic. “We also had a very competent Exxaro Resources safety officer on site. He went to the extra effort of alerting all couriers working in-and-around the area of the bypasses. The contract team also installed radar speed cameras typically deployed by the traffic authorities. They flashed at speeding vehicles, which slow them down, and this proved to be a very effective means of encouraging safer driving behaviour,” Visagie says. At the same time, a local emerging contractor was appointed to construct a 1km section of the district road, gaining valuable experience while working alongside an established principal contractor. MARCH 2019 MINING MIRROR [17]