Mining Mirror June 2019 | Page 19

Mine excursion available. With three excavators, our target is to mine about 10 500 cubic metres per day in two 12-hour shifts. Khanye currently operates until six on a Saturday morning on the mining operations, but we’ve applied for a continuous mining permit to enable us to mine on Sundays if required. Unearthing the coal CMS will use excavators and ADTs to load the coal, thus about three to four trucks per excavator, depending on the haul distance and turnaround time. “Because all three excavators are working close to each other you can swop trucks. Operators are trained to identify where they are needed the most when they arrive at the face. Our control room system allows the operator to report on an hourly basis what they have loaded (topsoil, shale, clay or coal). The system works well because South Pit is small. However, if there are 60 trucks and more excavators, you do need a more fixed and rigid system,” Thompson adds. Canyon Coal does all the blasting at Khanye in-house, but the drilling is done by a contractor called MEM. The company uses BME’s electronic blasting system. At the moment, they are drilling up to 13 000m per month including overburden, parting and coal. Thompson says that there is a lot of clay in the area and they have historically only been able to drill about 3 000m to 5 000m per month. “In the South Pit, however, there is a thick sandstone band, so our drilling increased more than three times last month,” he says. When Mining Mirror visited the site, the mine had blasted through the sandstone belt to expose 2 Seam coal. The sandstone material is used to build the mine’s haul roads. Blasting takes place as and when needed, but on average once or twice a week. Mining in the soft clay material in all three pits has limited the number of blasts required, but the clay also provides a challenge. The first coal seam (2 Upper Seam) in South Pit, is encountered at the bottom of the sandstone, about 9m from surface. Thompson says the clay causes what the miners refer to as “carry back” in the haul trucks. In other words, the clay gets stuck in the bin and needs to be cleaned out on a regular basis. “We have dedicated TLBs in the pits that clean the back of the trucks on a regular basis. If they don’t, the trucks deliver half loads,” explains Thompson. Processing the material The distance from the South Pit to the main processing plant is about 1.6km, which will be the longest haul, but the team is mining progressively towards the plant, which means the hauling distance will be reduced over time. There is a ROM tip area between the two plants from which both plants are fed. The bigger plant is a lot more advanced than the small modular plant, which produces an RB3 product of zero by 50mm.The new plant will normally target a 25.5 CV, but that will change to a 27 CV at certain times, as some coal seams are of a better quality than others, which means the products will be blended to produce a high quality export coal. Khanye’s new plant is the first of Canyon Coal’s larcodem plants built by contractor Obsideo and operated by Isimilo DBO, which consists of larcodems instead of the traditional drum plant, and a filter press to process the slurry. The coal mined in the pit is fed into the ROM feed bin. From there it goes through a primary crusher, then into a secondary crusher before it splits off into the larcodem that produces large and small nuts. After that the material enters a cyclone that handles the peas and the duff. Thompson explains that a secondary stage wash capacity is planned to be built within the main plant Khanye recently acquired a brand new fleet of Volvo Articulated Dump Trucks (ADTs). www.miningmirror.co.za JUNE 2019 MINING MIRROR [17]