LUSD Facilities Master Plan | Page 52

Section Three

F a c i l i t y A s s e s s m e n t s

Livingston Union School District | Facilities Master Plan

District Office

922 B St ., Livingston CA 95334 Andres Zamora , Superintendent
ID
Improvement
Construction Cost
Project Cost
The District Office building is located on the northern edge of Selma Herndon Elementary School . The location on B Street is close to downtown and can be found easily . Parking , however , is hard to find when the existing undersized parking lot is full . The parking lot is one-direction with slanted parking stalls . This requires a driver to enter only one drive entry and exit the other .
A larger parking lot is required , and it is suggested that the parking contain 90-degree parking stalls , which allow the traffic to use both drive approaches . 90-degree parking is also more efficient than angled parking . The steeper the parking angle the less efficient the parking lot capacity .
The District Office building is a comfortable building for its size . The issue with the building is that it ’ s too small for the number of employees it houses . Many of the employees should have private offices for personnel and privacy issues , but the current rooms are all shared by multiple occupants . The building can either be expanded with a building addition , or some of the employees moved out of the building to another suitable location . The idea of a building addition was reviewed in the Steering Sub-Committee , but it was determined it would be better to move some of the employees into the space now used by the Board Room .
Building BO ( Business Office ) has thee ( 3 ) offices and a large space used as a Board Room . In the Board Room space , there is enough room four ( 4 ) offices at around 130 square feet each . Adjacent hallways would serve as interior circulation and contain a 30-foot long working counter space and 20-feet of full height storage cabinets . It is suggested that the “ Board Room ” be located at the Prusso Child Development Center building or other suitable space .
The District Office building could use some remodeling in a few spots . Some of the existing spaces can be reconfigured to be more suitable in size and function . The Superintendent ’ s conference room would increase in size from 250 square feet to 410 square feet in size , and more suitable for meetings with up to 12 people . The two non-accessible toilet rooms would be combined into one accessible unisex toilet stall , about 90 square feet in size . The Technology MDF room serves the District Office buildings and the Selma Herndon school site . The Technology room would be increased in size to accommodate equipment / parts storage , with a dedicated cooling system required for the server equipment . The staff work room would be relocated from the back of the building adjacent the front office reception . The new proximity of the work room would be more suitable for the front office and other staff using this space at the core of the office . The only new square footage would be a 300 square foot building addition . The addition would allow the Superintendent to have a secure storage room for private records , and two toilet rooms would be included that could accessed from the exterior of the building .
Building and Site Improvements 1,761,000 2,179,000 Building Improvements 1,343,000 1,661,000
BO-REMOD
DO-1
DO-REMOD
DO-ROOF
" Business Office Remodel . Remodel portions of existing Business Office . Convert the existing Board Room open space into four ( 4 ) Offices . Replace Wall , Floor and Ceiling Finishes . New LED Lights and HVAC Ducts . 1,100 SqFt "
" District Office Building Addition . Add 300 SqFt of new building area . Toilet Rooms = 90 SqFt / Ea . Secure Storage = 100 SqFt ."
" District Office Remodel portions of existing building 1,300 SF Total area . Convert 2 Toilet Rooms into 1 Accessible Toilet Room , 96 SF Add Cooling to MDF Room , 267 SF . Convert Office space into a central Work Room , 260 SF . Remove 1 Office and enlarge Confer "
" District Office Roof System . Replace existing roof . Single Ply PVC 2,800 SqFt Include allowance for Dry Rot Repairs , 1,000 SqFt Plywood and Joists Replace HVAC Equipment and equipment curbs ."
320,600
218,600
378,900
102,000
DO-WALK " New concrete walks around the building addition ( DO-1 ). 500 SqFt ." 4,400
P-REMOD
" Remodel existing portable classroom into a Conference Room , 960 SqFt . Floor , Wall and Ceiling Finishes . LED Lights ."
279,800
DOORS Remove and replace all interior and exterior doors and hardware , 15 locations 32,800
VIDEO
" Provide a Video Surveillance system at the campus . Two ( 2 ) Cameras for each permanent buildings . No cameras at portables ."
Site Improvements 1,343,000 1,661,000
DO-PRKG
" Parking Lot 1 Reconfiguration . Pavement 17,200 SF , Concrete Paving / Ramp , 400 SF , Concrete Curbs , Parking Lot Signs 3 , Truncated Dome Mat 1 , Concrete Walks 17,000 SF , Landscaping 7,000 SF , Storm Drainage , LED Lights . "
5,800
401,000
FENCE Ornamental Iron Fence and Gates is part of the Selma Hendon Vision Plan 17,500
Totals 1,761,000 2,179,000
50