LUSD Facilities Master Plan | Page 52

Section Three

F a c i l i t y A s s e s s m e n t s

Livingston Union School District | Facilities Master Plan

District Office

922 B St., Livingston CA 95334 Andres Zamora, Superintendent
ID
Improvement
Construction Cost
Project Cost
The District Office building is located on the northern edge of Selma Herndon Elementary School. The location on B Street is close to downtown and can be found easily. Parking, however, is hard to find when the existing undersized parking lot is full. The parking lot is one-direction with slanted parking stalls. This requires a driver to enter only one drive entry and exit the other.
A larger parking lot is required, and it is suggested that the parking contain 90-degree parking stalls, which allow the traffic to use both drive approaches. 90-degree parking is also more efficient than angled parking. The steeper the parking angle the less efficient the parking lot capacity.
The District Office building is a comfortable building for its size. The issue with the building is that it’ s too small for the number of employees it houses. Many of the employees should have private offices for personnel and privacy issues, but the current rooms are all shared by multiple occupants. The building can either be expanded with a building addition, or some of the employees moved out of the building to another suitable location. The idea of a building addition was reviewed in the Steering Sub-Committee, but it was determined it would be better to move some of the employees into the space now used by the Board Room.
Building BO( Business Office) has thee( 3) offices and a large space used as a Board Room. In the Board Room space, there is enough room four( 4) offices at around 130 square feet each. Adjacent hallways would serve as interior circulation and contain a 30-foot long working counter space and 20-feet of full height storage cabinets. It is suggested that the“ Board Room” be located at the Prusso Child Development Center building or other suitable space.
The District Office building could use some remodeling in a few spots. Some of the existing spaces can be reconfigured to be more suitable in size and function. The Superintendent’ s conference room would increase in size from 250 square feet to 410 square feet in size, and more suitable for meetings with up to 12 people. The two non-accessible toilet rooms would be combined into one accessible unisex toilet stall, about 90 square feet in size. The Technology MDF room serves the District Office buildings and the Selma Herndon school site. The Technology room would be increased in size to accommodate equipment / parts storage, with a dedicated cooling system required for the server equipment. The staff work room would be relocated from the back of the building adjacent the front office reception. The new proximity of the work room would be more suitable for the front office and other staff using this space at the core of the office. The only new square footage would be a 300 square foot building addition. The addition would allow the Superintendent to have a secure storage room for private records, and two toilet rooms would be included that could accessed from the exterior of the building.
Building and Site Improvements 1,761,000 2,179,000 Building Improvements 1,343,000 1,661,000
BO-REMOD
DO-1
DO-REMOD
DO-ROOF
" Business Office Remodel. Remodel portions of existing Business Office. Convert the existing Board Room open space into four( 4) Offices. Replace Wall, Floor and Ceiling Finishes. New LED Lights and HVAC Ducts. 1,100 SqFt "
" District Office Building Addition. Add 300 SqFt of new building area. Toilet Rooms = 90 SqFt / Ea. Secure Storage = 100 SqFt."
" District Office Remodel portions of existing building 1,300 SF Total area. Convert 2 Toilet Rooms into 1 Accessible Toilet Room, 96 SF Add Cooling to MDF Room, 267 SF. Convert Office space into a central Work Room, 260 SF. Remove 1 Office and enlarge Confer "
" District Office Roof System. Replace existing roof. Single Ply PVC 2,800 SqFt Include allowance for Dry Rot Repairs, 1,000 SqFt Plywood and Joists Replace HVAC Equipment and equipment curbs."
320,600
218,600
378,900
102,000
DO-WALK " New concrete walks around the building addition( DO-1). 500 SqFt." 4,400
P-REMOD
" Remodel existing portable classroom into a Conference Room, 960 SqFt. Floor, Wall and Ceiling Finishes. LED Lights."
279,800
DOORS Remove and replace all interior and exterior doors and hardware, 15 locations 32,800
VIDEO
" Provide a Video Surveillance system at the campus. Two( 2) Cameras for each permanent buildings. No cameras at portables."
Site Improvements 1,343,000 1,661,000
DO-PRKG
" Parking Lot 1 Reconfiguration. Pavement 17,200 SF, Concrete Paving / Ramp, 400 SF, Concrete Curbs, Parking Lot Signs 3, Truncated Dome Mat 1, Concrete Walks 17,000 SF, Landscaping 7,000 SF, Storm Drainage, LED Lights. "
5,800
401,000
FENCE Ornamental Iron Fence and Gates is part of the Selma Hendon Vision Plan 17,500
Totals 1,761,000 2,179,000