Section Three
F a c i l i t y A s s e s s m e n t s
Livingston Union School District | Facilities Master Plan
Maintenance , Operations , Transportation Facility |
|
|
|
|
922 1 / 2 “ B ” Street , Livingston , CA 95334 Nick Jones , MOT Director |
ID |
Improvement |
Construction Cost |
Project Cost |
The Maintenance , Operations and Transportation ( MOT ) yard is situated behind Selma Herndon Elementary School . Most of the buildings are metal buildings , with metal skins .
Building 4 : the south bus shed , is clad with a wood siding , and this material will require painting to keep the siding in good shape to resist the weather . Building 4 also needs to have a minor building expansion so that the new longer buses can fit into the bus shed .
Building 5 is used by the Food Service Department . The walk-in cooler and freezer for the food storage are located inside the building and are is moderate condition . The doors have had some work and they will require future maintenance . The outdoor compressors and interior evaporators are at the end of their lives , and should be replaced soon . This could occur at the end of the school year when the need to store food is reduced .
Building 6 is used for the vehicle maintenance and the warehouse . Long term records are kept in the south portion , and the adjacent vehicle service bays could pose a threat for fire . If these records are of importance they should be scanned and / or moved elsewhere . The warehouse requires an upgrade to the rack and shelving so that the pallet boxes can fully rest on the shelves .
Building 7 is a new building to be used by the Grounds Department . The Grounds Department stores various supplies and equipment in a variety of locations within the MOT area . The new building would allow the Grounds Department to consolidate all equipment , supplies and resources . A large concrete area would be provided for equipment and equipment washout , and a dirt lay down area would be used for long term storage and plant storage / nursery .
Building and Site Improvements 1,565,000 1,936,000 Building Improvements 1,532,000 1,894,000
5-WI E
Walk-In Fridge and Freezer Equipment . Remove and replace existing walk-in Fridge and Freezer Compressors and Evaporators .
29,100
4-ADD Extend Bus Bays for longer buses . 600 SqFt . 87,400 4-PAINT PAINTING . Paint exterior building walls . T-111 wood siding . 4,000 SqFt 4,400
6-R + S
7-BLDG
" Industrial Storage Racks & Shelves Racks 4-bays tall x 110-LF x 48 "" Deep . Shelves 3 Bays x 50-LF x 24 "" Deep ."
New Grounds Bldg , 3,600 SqFt Metal Building . Concrete Drive 3,000 SqFt . HD Pavement 7,000 SqFt . Planter and Irrigation 3,000 SqFt . Chain Link Fence with Slats , 450 LF , & Motorized Rolling Gate .
46,600
1,311,500
7-R + S " Industrial Storage Racks & Shelves . Racks 4-bays tall x 160-LF x 48 "" Deep . " 46,600
VIDEO
" Provide a Video Surveillance system at the campus . Two ( 2 ) Cameras for each permanent buildings . No cameras at portables ."
Site Improvements 34,000 41,000
PAVEMNT Slurry Seal Pavement , 9,200 SqFt . 33,500
Totals 1,565,000 1,936,000
5,800
48