Prusso Child Development Center
Section Three
F a c i l i t y A s s e s s m e n t s
Livingston Union School District | Facilities Master Plan
Prusso Child Development Center
848 Prusso St , Livingston , CA 95334 Ages : 3-5 Years old
The Prusso Child Development Center building serves the younger children within the City of Livingston . The east side of the building has a set of classroom spaces that are used daily for preschool education . The remainder of the building is not utilized on a regular basis . The rest of the building has a large multi-purpose building with a stage , a food preparation Kitchen and another set of classrooms . The building was designed and constructed in the early 1970 ’ s and most of the material finishes and conditions are vintage 70 ’ s style .
The stage was used in the past when the adjacent school was used as Livingston Middle School . However since a new middle school was opened in 2000 , the stage is rarely used . The stage area is too small to be an effective stage for performances and events . To make the stage more usable it would need to be larger in area and include space for stage storage .
In the vision plan , the existing stage would be converted to stage storage , and a new stage with proscenium walls would be added into the existing multi-purpose space . The proposed vision plan has a stage that is 1,300 square feet and the stage storage space would be about 800 square feet . The stage storage area would be equipped with large cabinets for music equipment and a large sink for cleaning out instruments . The stage storage would also allow for the use of stage props to be brought back and forth onto the stage for performances .
The existing Multi-Purpose room is about 5,000 square feet , and after the stage is carved out , the remaining space would be around 3,200 square feet . The Multi-Purpose Room and new stage could be used for school plays , celebrations , staff development meetings , workshops , community events and Board meetings . The adjacent parking lots for the baseball field and the elementary school could be used for overflow event parking . The large open MPR space would need to include some acoustical design elements , including a sound system and a stage lighting system for effective use .
The existing parking lots require a new slurry seal and restriping . The accessible parking stalls are no longer in compliance with the code , and need to be upgraded for code compliance ; new signs and striping . A new parking lot would be added to the west end of parking lot 1 , and this would be used to service the County Office facility .
ID Improvement
Construction Cost
Project Cost
Building and Site Improvements 2,520,000 3,117,000 Building Improvements 2,321,000 2,871,000
CLASS-1
CLASS-2
ENTRY
" Classroom # 1 Remodel / Upgrade . 1,050 SqFt Total . Remove and replace Carpet . Replace Wall and Ceiling Finishes . LED Lights . Replace exterior windows . Add Furred wall with Insulation at exterior walls ."
" Classroom # 2 Remodel / Upgrade . 525 SqFt Total . Remove and replace Carpet . Replace Wall and Ceiling Finishes . LED Lights . Replace exterior windows . Add Furred wall with Insulation at exterior walls ."
" Upgrade Interior Finishes & Doors , Ceilings and Walls , 2,400 SqFt . Polished Concrete 2,400 Sqft , LED Light Fixtures , Replace Doors + Hardware 20 . Replace Storefront Entrance System ."
114,800
57,400
174,900
KIT " Kitchen Upgrade . 525 SqFt . Remodel Kitchen and new Kitchen Equipment ." 153,000
MPR
PRE-R
PRE-TR
ID
REFRESH
STAGE-1
STAGE-2
TOILETS
Improvement
" MPR Room Upgrades , 4,300 SqFt Total . Replace VCT Floor with Rubber Flooring . Add Sound Panels to CMU Walls . Add LED Lighting and Sound System . Add Acoustical Ceiling Sound Cloud Tiles . Remove Basketball Hoops . Paint upper 6-feet of walls , and ceiling surface "
" Pre-School Remodel / Upgrade . 2,100 SqFt Total . Remove and replace Carpet . Replace Wall and Ceiling Finishes . LED Lights . Replace exterior windows . Add Furred wall with Insulation at exterior walls ."
" Pre-School Toilet Room Remodel / Upgrade . 400 SqFt Total . Reconfigure room for access compliance "
" Upgrade Interior Finishes & Doors Ceilings and Walls , 2,400 SqFt . Polished Concrete 2,400 Sqft , LED Light Fixtures , Replace Doors + Hardware 20 . Replace Storefront Entrance System ."
" New Stage , 1,300 SF . Construct new Stage area inside the existing MPR space . Requires a vertical lift , new stage steps , stage curtain , stage project screen and A / V system , sound system and stage lighting system . Electrical and Data outlets on stage for mee "
" Stage Remodel / Upgrade , 800 SF . Remodel existing stage area into a Stage Storage space to serve the new Stage . Large cabinets for music equipment storage . Add a sink for instrument cleaning . Electrical and Power Outlets . Replace Coiling Exterior Door 20 '"
" Toilet Room Remodel / Upgrade . 275 SqFt Total . Reconfigure room for access compliance "
313,300
229,500
58,300
174,900
189,400
87,400
40,100
ROOFING Remove and replace roofing system . 14,000 SqFt . 510,000 SIGNS " Add Accessible Room ID Signs , Add Accessible Toilet Room Signs . 25 Signs " 6,400 FANS " Remove and Replace all exhaust fans in toilet rooms . 6 locations ." 8,700
HVAC
VIDEO
P . A .
" Remove and Replace HVAC Equipment & Equipment Curbs . 2 Package Units , 10-Tons each . 8 Package Units 2 Tons Each ."
" Provide a Video Surveillance system at the campus . Two ( 2 ) Cameras for each permanent buildings . No cameras at portables ."
" Add new Public Address system . Speakers in all Classrooms and occupied spaces . 8 Exterior Horns "
145,700
5,800
21,900
F . A . " Replace Existing Fire Alarm System , District Standard - Gamewell FCI " 29,100
Construction Cost
Project Cost
Site Improvements 199,000 246,000
1-PRKG Parking Lot 1 - Slurry Seal and Re-stripe , 8,500 SqFt 31,000 2-PRKG Parking Lot 1 - Slurry Seal and Re-stripe , 15,200 SqFt 55,400
3-PRKG
" New Parking Lot 3 . Add Nine ( 9 ) Stalls . Pavement 4,000 SqFt . Concrete Walk 1,400 SqFt . LED Pole Lights , 2 . Remove and replace chain link gate with an Accessible Gate ."
93,300
SHADE Play Area 1 Fabric Shade Structure , 30x30 19,700
Totals 2,520,000 3,117,000