K I NG S G AT E PA R K
Phased Development
PHASE 1: Page 12
Support Departments PHASE 2: Page 14
New Sports Centre PHASE 3: Page 24
Design Technology and Sanatorium
After relocating vehicular access from
Kingsgate Road to Norman Road, 2. Demolition of existing Physical
Education Centre. 1. Construction of Support Departments’
buildings: Construction of new Sports Centre complex,
starting with Once the project’s primary objective – the new
Sports Centre complex – has been delivered,
attention will shift in due course to
• Works Department
• Central Purchasing Department
• Energy Centre
• Laundry
• Grounds and Gardens Stores
• Furniture Store
• Waste and Recycling.
7. D
esign Technology extension
3. Swimming Pool building, followed by 8. Design Technology refurbishment
4. Sports Hall building, followed by 9. Construction of a new Sanatorium
5. Fitness Suite, then 10. Redevelopment of Antrim House.
6. Conversion of existing Fives Courts
to other school use.