Kingsgate Park Sports Centre KP Brochure | Página 7

K I NG S G AT E PA R K The schedule and cost 2019 2022 Cost SUMMER Project officially begins on site SPRING Sports Centre complete Total cost of the Sports Centre: £40 million Building of the temporary facilities including the new Cricket Pavilion (1) WINTER Removal of equipment from the current PEC to the temporary facilities Demolition of the existing PEC (2) Construction of the new Sports Centre commences Comprising: Swimming Pool Pavilion (3) Sports Hall Pavilion, including the Cecil Rifle Range (4) Fitness Pavilion (5) ~ 6 ~ The timings and cost are based on estimates at May 2019 and may be subject to change.