Key Biscayne Master Plan 043944000.18w_Key_Biscayne_MP(forJooMag) | Page 91
Chapter 9
T R AN SPORTATIO N MA N A GE M E NT PL AN
A Transportation Management Plan (TMP) has been developed to
coordinate traffic impacts related to both the undergrounding program
and other known significant infrastructure projects for each phase/year
of the construction to minimize impacts to the residents and businesses.
Based on the proposed undergrounding project phases and other
known infrastructure projects (by the Village and others), Kimley-Horn
has assessed the traffic impacts from construction for each phase of
the project. The following section describes the methodology utilized to
develop the TMP, as well as overall guiding principles (general guidelines)
for use by the Village and affected contractors during the implementation of
the undergrounding program.
STAKEHOLDER —
COMMUNICATION CONTACTS
Further communication with the following stakeholders is
recommended as the TMP evolves throughout the implementation
of the program:
The TMP is a specific set of strategies to manage the work zone impacts
of a project. Its use may evolve over time, but its current role is to assist in
the development of the design of construction phasing plans, traffic control
plans, and project specification documents, and to facilitate discussions
between the Village, designers, utility owners, contractors, and other
key stakeholders related to traffic impacts. It should also be used by the
Village as a tool during the maintenance of traffic (MOT) permitting process
to better coordinate construction traffic impacts as specific permits are
applied for by the construction community.
Graphics and/or boards of the proposed TMP strategies are recommended
for use during the public outreach process. An overall TMP, as well as
general traffic control guidelines for the program, were also developed. The
TMP strategies follow standard MOT guidelines, schematic in nature, and
are displayed on GIS maps in this section.
9.1
Village of Key Biscayne Police Department
Various Key Biscayne Homeowners Associations
Village of Key Biscayne Fire Department
Village of Key Biscayne Public Works Department
Village Manager’s offi ce
Undergrounding Utilities Task Force
Village Council
Utility companies (FPL, AT&T, Comcast, Hotwire)
Outside utility providers: Miami-Dade County Water and
Sewer Department, Miami-Dade Public Works, AmeriGas,
and American Traffi c Solutions
Commercial businesses: (i.e. commercial district
businesses, hotels, country clubs, etc.)
Roadway Network
The roadway network within the Village is described below.
The main north-south thoroughfare is Crandon Boulevard that connects
the Village with the mainland through the Rickenbacker Causeway to the
north and ends at the Bill Bags Cape Florida State Park entrance.
87