Key Biscayne Master Plan 043944000.18w_Key_Biscayne_MP(forJooMag) | Page 60

VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES — MASTER PLAN Because of how the Village was originally developed and the configuration of the land mass and roadways, it would be easy to have two adjacent work areas undergoing heavy construction at the same time, impacting a large area of the Village at once. A good deal of consideration and strategy went into developing a sequence that avoided just that. To that end, Kimley-Horn recommends that heavy construction activities do not take place simultaneously in two adjacent phases. For example, as Phase 1 heavy construction ends, Phase 2 heavy construction can begin, and so on and so forth. Heavy construction refers to the installation of the conduit and equipment pads either by open trenching or directional drilling operations. While heavy construction activities are taking place in Phase 2, less impactful activities can take place in Phase 1 such as equipment installation and demolition of existing facilities. In this manner, a motorist can avoid roadways experiencing heavy underground construction and will never have to drive through two phases undergoing heavy construction activities at the same time. 6.2.3 Cost Efficiency In determining the sequence of the phases, cost efficiency was also a priority. At the completion of each phase, there will be a transition from the new underground system to the existing overhead system to maintain connectivity of the systems after the de-energized poles are removed. These transitions almost always require the installation of new temporary poles with electric and communication risers. Because these new poles are temporary and will be removed when their location phase is completed, it is important to minimize the number of transitions to the greatest extent possible. by overlapping phases wherever possible while avoiding significant traffic impacts to the extent practical. 6.2.4 Schedule Considerations As discussed in the Physical Size of the Individual Phase section, individual phases were developed considering work that could reasonably be performed in an 18 to 24-month continuous period. To gain schedule efficiency, Kimley-Horn recommends work in adjacent phases overlap each other to avoid waiting until final completion of one phase before beginning work in a subsequent adjacent phase. This recommendation is discussed in further detail in the Overall Program Opinion of Schedule section of this master plan. In general, this would allow for service conversion work and overhead infrastructure demolition to occur in one phase, while heavy underground work would occur simultaneously in the adjacent phase. In no case do we recommend heavy underground work be performed simultaneously in adjacent phases. This avoids significant traffic impacts expected if these activities were allowed to occur simultaneously in adjacent phases. Phases in the commercial areas of the Village are anticipated to be more technically challenging from a design and easement acquisition standpoint. This is due to the high electrical load demand, limited right-of-way availability, and urban landscape. Fortunately, the way the commercial property is situated in the Village, we were able to divide the commercially zoned areas into three different phases, effectively reducing the complexity in any one phase. This will allow adequate time for design and easement acquisition for these challenging parcels. In order to do this, phases should be constructed sequentially so only one side of the phase area would require these transitions. The sequencing this master plan recommends accomplishes this by constructing phases generally starting from the south end of the Village moving towards the north. This will also minimize the amount of temporary facilities the communication utilities need and generally accommodates their preferred sequence of conversion. In addition, compressing the schedule as discussed in the following section will reduce costs due to inflation and project general conditions. The sooner the program is complete the less inflation factors into the overall budget. We recommend accomplishing this FPL capacitor bank 56