VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES — MASTER PLAN
Collection of data related to planned, major construction projects
within the Village Development of design criteria to be followed throughout the
duration of the undergrounding program Development of a conceptual opinion of probable construction cost
for the program
Development of an implementation plan for new underground
facilities to serve as a guide for the future detailed design phases Coordination with key project stakeholders to develop the
master plan
Identification of infrastructure projects that could be constructed
concurrently with the undergrounding program to take advantage
of restoration cost sharing Assessment of the risks associated with the undergrounding
program along with risk mitigation strategies
Performance of public outreach to inform the community about the
undergrounding program
Development of a sequencing and phasing plan that identifies both
the phase area limits and a conceptual schedule of activities for
each of those phases
Development of a traffic management plan that coordinates the
undergrounding activities with other known significant construction
projects to reduce traffic impacts during the implementation
process
The following sections of this master plan will describe each one of these
goals in greater detail along with our recommendations for implementation
of the program.