Key Biscayne Master Plan 043944000.18w_Key_Biscayne_MP(forJooMag) | Page 115

11.0 OVERALL PROGRAM OPINION OF SCHEDULE OVERALL SCHEDULE HIGHLIGHTS  The program schedule began in March 2018 with the development of this master plan.  Detailed design will need to start as soon as practical to minimize the duration and completion date of the program.  Design begins earlier for subsequent phases before prior phase completion to allow more time for the easement acquisition process.  Construction Manager selection occurs prior to fi nal design completion to allow them the opportunity to provide constructability reviews and make value engineering suggestions.  The design of the communications networks follows the design of the electrical network to allow coordination of the designs that promotes the collocation of electrical and communications equipment in common easements. This reduces the overall number of easements required for the program.  Construction activities for the program are expected to kick off in the summer of 2020 with Phase 1.  Construction durations for each phase range from 18 to 24 months depending on the quantity of work to be performed and complexity of each phase.  In order to accelerate the schedule, the construction phase for Phases 2, 3, and 4 of the program overlaps the previous adjacent phase construction schedule by a minimum of 6}months with potential to overlap 12 months or more.  The overlap of the construction activities in each phase is subject to “heavy” construction being complete in the previous phase prior to allowing “heavy” construction activities to begin in the subsequent phase. This is done primarily to mitigate community and traffi c impacts.  The fi nal six months of the construction activity schedule for each phase is reserved for switch over, pole removal, and fi nal restoration. It is not expected that this will be a continuous construction activity. Experience with similar projects has shown that the coordination required with FPL, AT&T, and Comcast can be time consuming and therefore requires a duration of time for the switch over and pole removal to be accomplished.  All areas of the Village are scheduled to be converted to an underground system by the middle of 2025. Final pole removal is scheduled to be completed by the end of the second quarter in 2026.  The schedule does contain time contingencies for normal weather impacts, soil conditions, and typical unforeseen conditions. It does not account for signifi cant schedule impacts related to signifi cant weather events that cause the utility owners to focus efforts on storm recovery rather than undergrounding. It also does not consider signifi cant contractor issues related to litigation, bankruptcy, non- performance, and the like because these types of issues are impossible to predict. 111