VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES — MASTER PLAN
and Miami-Dade County as needed to receive approval at least
21 days in advance of the contemplated activities that may impact
those jurisdictions.
98
Material hauls on local streets will be subject to the Village of Key
Biscayne’s requirements and local ordinances.
After approval of traffic control plans and associated closures and
detours on Crandon Boulevard, the contractor shall place advance
closure notice information signs per Village of Key Biscayne and
FDOT requirements and advise affected businesses, residents,
and stakeholders at least two weeks in advance of impending
approved closures.
In all cases where there are roadway impacts, the contractor shall
assure access is maintained or otherwise provided to and from
abutting properties. After approval, the contractor shall advise
residents and businesses of any impending access restrictions. Full
closure of roads in a manner that prevents access to residences
and businesses will not be permitted.
Temporary traffic control devices shall not be set up in advance of
a closure unless approved by the Village. Upon completion of the
closure, traffic control devices shall be removed from the roadways
and shoulders by the end of the work day. The devices may not be
left or stockpiled on shoulders or in clear zone areas.
The contractor shall provide schedules of daily activities and
corresponding traffic control plans. This information shall be
provided in advance and during construction progress meetings.
The information provided shall specify the limits of the work
activities and related traffic control plan by location, direction, and
time. The construction schedule and associated traffic control plans
shall be developed in a format suitable for release to other agencies
and the public, and shall be updated as necessary.
Contractors will remove all traffic control for temporary lane
closures prior to holidays or weekends that adjoin a holiday.
Lane closures that require an extended duration and are
implemented with appropriate barriers, traffic control devices, and
signage shall be allowed to remain in place during a holiday or
holiday weekend.
Special Events
Partial or full closures on corridors are not allowed when a special
event occurs within that roadway corridor.
Emergency Services
Field personnel shall coordinate with emergency services for any
partial closure where no shoulders are available.
Detour routes shall be communicated to emergency services on a
weekly basis, or more frequently as the detour routes change.
Special Approval
The Village Public Works Department must approve any
exceptions.
Any requests for special exceptions shall be made with four weeks
advanced notice to allow time for a thorough review and approval,
if required.