Kattumaanap Poriyaalar october 2013 | Page 46

requirements. Such absurd provisions as asking for a performance guarantee from the contractor without the other party giving a counter guarantee for prompt payment is not fair, though the contractors sometimes agree to this requirement. Each party should be very careful in making changes in the standard format which run in its favour but to the detriment of the other party. 7. Specific Relief Act : If there is a contract and one party is not performing its obligations or unwilling to do so while the other party is willing and is performing its obligations under the contract, the aggrieved party can go to court under this Act and compel the unwilling party to cooperate. 8. Dispute Settlement under the Indian Arbitration Act : Though it is not the order of the day, disputes do arise due to various reasons between the parties concerned. Some of these disputes may be over minor matters and can be resolved amicably if both the parties sit across the table and talk over the things. This is frequently not done. It would be advisable to have weekly meetings at the site, in which in additions to the discussions on progress and quality, any grievance that one party may have against the other may be brought up, discussed and settled. If these are settled, the minutes of meetings should be recorded and signed by both the parties. Now let us look at the causes of the disputes. (a) Delay in the payment of bills by the Owner and the consequent slowing of works by the Contractor: In the contract agreement, it is stated that after a certain minimum arnount of work is done, (expressed in value) the Contractor is entitled to submit a bill and the payment procedure is stated. If the bill has been checked by the person authorized by the Owner, then prompt payment should be made. If the Owner delays the payment of one or more bills, or pays them only partly, and conceals the fact from the Contractor that there is difficulty in cash flow, the contractor will not carry on at the same speed of construction. The remedy is either to pay the bills promptly or to rework the construction schedule. (b) Fixation or the rates for extra items and payment for the same : The contract specifies that an extra item will be carried out by the Contractor only when it is properly authorized and the rates are settled. Frequently, the Contractor delays the submission of rate analysis for the extra items for various reasons and later submits a bill at high rates. The contract specifies how the rates for extra items have to be worked out. These instructions have to be strictly followed and the cause of disputes eliminated. (c) Payment of escalation : The contract has clauses (10c and 10c and the CPWD format) for the payment of labour and material escalations. The period over which these are payable is given in the agreement. If the formula according to which the calculation of escalation payable is to be made, is typed or printed in the contract document wrongly, the Contractor should seek clarification before signing the Agreement and not raise the issue at a later date, but he frequently does as also over the period for which escalation is payab