In the control chart for a program test, all of the lines have leveled off, as in the diagram below. Which of the following is the appropriate interpretation of this state? No. of test items No. of bugs No. of bugs detected No. of incomplete test items No. of unresolved bugs Q55. Time a) The outostanding bugs are difficult to resolve, so there has been no progress with the subsequent test. ) b The track record for completed test items has reached to the point where no more bugs will be unovered. ) c Bugs are encountered, so the track record of completed test items cannot be improved. ) d The ratio of bug detection and test item completion are the same, so there are no unresolved bugs. Q56. Which of the following is the correct description of the scope? a) The final deliverables of the project, and the scope of work required to produce the deliverables b) To breakdown the organization for a project, and express them in a hierarchical structure c) To monitor the budget and work progress, and quantitatively evaluate the progress of the project d) To reassess the work schedule that is decided by the project plan document Technology Q57. Which of the following is the appropriate description of information security policy? a) Describes the procedures for implementing the security level determined by the organization. b) Necessary to prevent information assets from various threats. c) Establishes the order of potential risks in using information systems, starting with risks that have the greatest probability and the greatest loss. d) Upper management explains the organizational approach and initiatives for the information security to the employees. 323