5-3 Which of the following is described in a project plan? a) b) c) d) 5-4 It takes 24 days for Mr. A to complete a certain software development and 12 days for Mr. B. When both Messrs. A and B work together, 25% of all the working hours in a day are needed for preliminary discussion. When both Messrs. A and B work together, how many days does it take to complete the development? a) b) c) d) 139 Screen layout Workflow Schedule Program structure 6 8 11 12