5-3
Which of the following is described in a project plan?
a)
b)
c)
d)
5-4
It takes 24 days for Mr. A to complete a certain software development and 12 days for Mr.
B. When both Messrs. A and B work together, 25% of all the working hours in a day are
needed for preliminary discussion. When both Messrs. A and B work together, how many
days does it take to complete the development?
a)
b)
c)
d)
139
Screen layout
Workflow
Schedule
Program structure
6
8
11
12