ITEE ITEE-1 | Page 141

In the following arrow diagram example, work E can be started when work C and work D are both finished. In other words, work E can be processed seven days after the work is started. Work A Work C 2 days 5 days Work B Work D Work E 2 days 3 days 2 days Example In the following arrow diagram, calculation for the overall number of days required if work C can be shortened to three days is illustrated. Work A Work C 2 days 5 days Shortened to 2 days Work B Work D Work E 2 days 3 days 2 days The overall number of days required is calculated as follows (before work C is shortened to three days). Work A (2 days) + Work C (5 days) = 7 days Work B (2 days) + Work D (3 days) = 5 days Seven days are needed until both work C and work D are finished, so the overall number of days required is: 7 days + Work E (2 days) = 9 days. If work C is shortened to three days, at most five days are needed until work C and work D are finished. Therefore, the overall number of days required is: 5 days + Work E (2 days) = 7 days. 135