LAke victoria watsan project
ational Water and Sewerage Corporation has identified a need to increase the capacity of water in the central region,
specifically in areas of Ggaba, Muyenga and Naguru so as to solve water supply challenge. CES Consulting Engineers Salzgitter GmBH are the main consultant on the project “Rehabilitation and Water Production Capacity Optimization of Ggaba Water Treatment Complex and Transmission Mains Improvements with donor-funding from KfWEntwicklungsbank for a total project sum of 36 million Euro. Interface is providing Clerk-of-Works services on the project.
Works include
•
•
•
•
•
•
The implementation of these measures will raise the production capacity, the treatment processes in all the three Plants will be optimized and their operations become more stable, with better quality treated water.
Project Details:
Client: National Water and Sewerage Corporation
Partners: CES Consulting Engineers Salzgitter GmBH
N
"Improving Access to Better Quality Water"