Ingenieur Vol.72 ingenieur October 2017-FA3 | Page 52

INGENIEUR Systematic Approach To Mechanical Completion Execution In the Oil And Gas Industry By Ir. Roslin Bin Ramli Principal (Construction) Project Delivery and Technology (PD&T), PETRONAS T he article is expected to improve construction technology for companies with the following benefits:- • C o n s t r u c t i o n I n f o r m a t i o n a n d Communication Technology (CICT) in Mechanical Completion • Establishment of Mechanical Completion Standard in the Oil and Gas Industry • Creation of skilled manpower in construction technology A systematic approach to mechanical completion execution in the oil and gas Industry will enhance the competitiveness of industries, the protection of consumers and the environment, and has been the mainstay of PETRONAS endeavours in the implementation of its standardisation and quality programmes. PETRONAS’ Triple Plus Elements comprising Leadership, Capability Development, Mindset and Behaviour Change are applied in developing this systematic approach. PROJECT BACKGROUND OVERVIEW Project Description To establish a standard guideline in the Mechanical Completion Execution handover process in the Oil and Gas Industry by: • ensuring the safe introduction of hydrocarbons before “Plant Start-Up”; 6 50 VOL 2017 VOL 72 55 OCTOBER-DECEMBER JUNE 2013 • allowing pre-commissioning activities to commence prior to Mechanical Completion; and • maintaining consistent monitoring and verification activities to ensure that commissioning work commences only after construction activities and mechanical completion integrity checks have been completed. Project Problem Statement In the typical construction of a building, facility or plant in the oil and gas industry in Malaysia, three main parties are involved i.e. the project owner, the Project Management Consultant (PMC), and the contractor. Mechanical Completion is one of the project milestones that has to be achieved and is defined as that point in time when the total facility has been fully constructed so that the whole facility is ready for commissioning. In mechanical completion, the problems that usually arise are: • current procedures and guidelines are not specific enough which result in inconsistencies during implementation; and • variation in guidelines from the owner and contractors create inconsistencies in executing mechanical completion. The impact of variations in the guidelines are: i) delays in commissioning and the Provision Acceptance (PA) of the project;