Ingenieur Vol 62 April-June 2015 Ingenieur Vol 62 April-June 2015 | Page 45

In Dakin v Lee [1916] 1 KB 566, a builder sued for payment for works done to a defendant’s house. The builder was held entitled to recover the payment, less an appropriate deduction for the cost of remedial works. Duquemin Ltd v Raymond Slater [1993] 65 BLR 124 was another case in which the doctrine was applied. There, a contractor carried out refurbishment and extension works. The arbitrator awarded the employer a larger sum by way of abatement for defects than the value of the contractor’s claim. The court decided that the arbitrator had acted beyond his jurisdiction, and that the greatest possible abatement was to reduce the contractor’s claim to zero. In Mellowes Archital Ltd v Bell Projects Ltd [1997] 87 BLR 26, a sub-contractor sought summary judgment for sums due on an interim application. The Court of Appeal held that the main contractor was not entitled to use its delay claim as abatement and the sub-contractor was granted summary judgment. Buxton LJ reviewed the law of abatement at length in coming to such a holding. He said that the measure of abatement must be limited to the difference in value of the thing itself. The cost of repairing damage to anything else other than the thing itself is not recoverable. ARE INTERIM CERTIFICATES SPECIAL? In Dawnays v Minter [1971] 1 WLR 1205, Lord Denning MR made some general observations, which were not essential to the decision in the case, and vW&RF