HIGH PROFILE
Finding # 1: grading results last longer than expected
Each graded stretch was compared with itself. For a week before the job, roughness sits flat. The day after, the road is 7 % smoother, and it is still 6 to 8 % smoother two weeks later. On the busiest roads, though, the graders return within days( see graph below).
Finding # 3: graders can’ t repair damaged roads
A third of all blading time, 34 %, went to stretches that actually need repair, where grading brings little or no benefit( see graph below). Graders do not waste much time on good roads: only 6 % of blading went to class A or B.
Finding # 2: road class A-E prescribes optimal grading strategy road quality
A – B Leave it
C One 20-minute job
D About 10 minutes
E 10 minutes, test first
B road quality
B
C road quality
road quality
C D
D E
What stands out is that 85 % of the blading time went to 46 % of the graded roads. A grader typically returned to any road segment after a few days, while the RoadGuard measurements show one visit’ s gain may last nine days or more. By that measure, the graders seem to return sooner than the road needs; whether that also holds on the busiest roads is for a trial to test. Meanwhile 40 % of the rough road segments received no detected grading at all: blind spots until now. However, only six graders carried trackers, so some grading may not have been recorded.
Where is the value?
0 |
10 |
20 |
30 |
|
|
|
|
|
|
|
|
|
|
|
|
0 |
10 |
20 |
30 |
|
|
|
|
|
|
|
|
|
|
|
|
0 |
10 |
20 |
30 |
|
|
|
|
|
|
|
|
|
|
|
|
0 |
10 |
20 |
30 |
grading time( minutes) |
grading time( minutes) |
grading time( minutes) |
grading time( minutes) |
80 % confidence interval start of job recommended job length
Does more blading buy better roads? Not necessarily. Graders move the needle most on C and D roads: C needs a proper job of about 20 minutes, D shows an optimum around 10 minutes. A and B roads stayed the same or slightly worsened after more grading. E roads may improve after the first few short jobs but then hit a wall. Grading them again does not lift them further. Those sections need repair, not grading.
The main win is grader time. If a short job every 10 days holds a road as well as today’ s more frequent visits, the same road may only need half of today’ s blading hours. The freed hours can go to the blind spots: grading every rough stretch would give trucks up to 20 % more of their driving time on recently graded roads, with fewer total grader hours than today.
A smoother road also lowers rolling resistance and raises the trucks’ average speed slightly.
How to implement?
Job length and revisit schedule by road class
On most roads the measurable gain sits in the first visit. Extra blading may still clear rock spillage, which Muruntau’ s operators often report and vibration cannot see, but it buys no measurable improvement in road quality.
The optimised daily worklist, ranked by road condition and traffic, will concentrate blading on C and D roads, where it does most, and leave A and B roads alone, where it only slows traffic. An E section gets a test: three short jobs within about 10 days. If it gains five points, it joins the normal rhythm; if not, it goes onto the repair list.
The first step the measurements suggest is to blade the busiest corridors less often. NMMC will test it on one busy corridor for a month: the trucks equipped with RoadGuard will show within days whether the road holds and, if it does not, the grader goes back. The freed hours go to the blind spots.