MINING EPCM
Finding the sweet spot
One constructability approach cannot be used for an entire mining project, according to Wood’ s Peter Kelsall, with part of a project potentially modularised, part preassembled and other parts‘ flat packed’ or stick built( Credit: Getty Images, zozzzzo)
When it comes to feeling the benefit of early-stage contractor involvement in the EPCM space it is all about timing, Dan Gleeson reports
Engineering, procurement and construction management( EPCM) has become a catchall abbreviation in the mine engineering and development space, with firms coming under this umbrella doing much more than the acronym would imply.
Many of these companies get involved as early as the scoping study / preliminary economic assessment stage and, similarly, continue to impart wisdom and experience beyond the commercial production milestone.
For IM’ s annual mining EPCM focus, we spoke to leaders at two such firms to scope out the industrial landscape in mining.
Securing the‘ A Team’
Speaking of early engagement, one of the first questions IM put to Peter Kelsall, Project Director at Wood, was around the value generated for clients that signed Early Contractor Involvement – or ECI – contracts ahead of the official EPCM stage kick-off.
Kelsall said this process, which is commonly referred to in project discussions, is one he has often used with clients.
“ Yet, it occurs at different times of the project lifecycle, and the terms of reference will vary depending on the project’ s ambitions and the client requirements,” he said.
Some of the more significant ECI scopes Kelsall has been involved with have been as part of the kick-off for the Detailed Design of the project.
He explained:“ The ECI process at this stage is effective as the design is mature enough to be able to evaluate the layout of the plant along with information of the major equipment and the major installations becoming available. This means that the discussion on high-level objectives and opportunities becomes focused on the actual assessment of how these can be implemented for this project.”
The reason why an ECI pact is seen as valuable to a project more broadly is to bring an early focus to the“ constructability” of the project, especially combining this with the contractors’ capabilities, the project location, the logistics challenge, etc.
“ This will result in all projects knowing the challenges associated with their project and the options that can be implemented,” he said. There are some caveats here.“ The fact is that one constructability approach cannot be used for the entire project; there can be part of the project that can be modularised, part pre-assembled and others‘ flat packed’ or stick built,” he said.“ Based on schedule and the status of the detailed design and equipment procurement, the ECI process, by working with the engineers, enables the‘ agreed best for project approach’ to be developed.”
This agreed best-for-project approach will mean there is an improvement to cost or schedule, or both, which is a key ECI value driver, according to Kelsall.
He added:“ The ECI process enables the contractors to have an enhanced understanding of the scope of the project, which then enables a greater understanding of the project execution requirements and an earlier alignment on the risk profile and, therefore, greater time to develop and implement mitigations. Likewise, it enables the earlier identification of opportunities in a timeframe that enables them to be embedded into the project.”
The early focus on constructability and aligning the procurement plan also has a proven outcome in improving the safety and quality of the delivery of the