IM 2022 August 22 | Page 8

WORLD PROSPECTS
40,000 t of primary sulphide material averaging 0.4 % Cu – containing more than 90 % chalcopyrite – that , using the same process outlined by Muchnik , showed consistent recoveries of over 70 %, he said .
Asked if the company is eyeing even higher recoveries that can compete with the levels Cuprochlor is achieving on secondary sulphides , Muchnik said it was all about an economic tradeoff . “ It may be possible to hit such a percentage [ as Cuprochlor ], but that is not the aim or expectation with the kinetics we are currently seeing in Cuprochlor-T ,” he said . “ There is always a tradeoff between the length of irrigation time , the PSD and the recoveries , all of which are related to capital costs , operating costs and the payback associated with the process .”
The Antofagasta planning and operations teams have now got their hands on the Cuprochlor-T ‘ licence ’ and will be busy outlining potential deployments for consideration in the company ’ s annual planning cycles .
There are some obvious places to start . The Zaldívar open-pit , heap-leach copper mine , 175 km southeast of Antofagasta , is currently in the process of transitioning to chloride leaching
operations with Cuprochlor . The project , which includes an upgrade of the SX plant and the construction of new reagent facilities and additional washing ponds for controlling chlorine levels , was completed in January 2022 and is now being commissioned . It is set to boost copper recoveries by approximately 10 percentage points , increasing production at Zaldívar by around 10,000 – 15,000 t / y over the remaining life of mine .
“ In addition to transitioning to chloride leaching with Cuprochlor for secondary sulphides , we are currently progressing studies for the primary sulphide orebody that currently lies below the Zaldívar reserves to prove if Cuprochlor-T leaching can work ,” Muchnik said . “ Within our resource base , there are approximately 460 Mt of primary sulphide resources declared here .”
Both Centinela and Antucoya have primary sulphide resources and existing heap leach and SX-EW facilities that would fit the Cuprochlor-T blueprint too .
Muchnik said : “ One of the technology attractions of Cuprochlor-T is the ability to use otherwise idle leach pad and SX-EW capacity . That it is the scale limitation at our current operations , but the technology can be gradually deployed
within a plant that is already adapted for chloride leaching , phasing this in during the life of mine to fit requirements . It provides an ongoing adoption process option rather than an immediate infrastructure project that sees an operation shift from oxide leaching to a different kind of heap leaching in one go .”
The advent of Cuprochlor-T does not mean the company will completely drop potential concentration projects , Muchnik clarified , highlighting the second concentrator project currently subject to a feasibility study at Centinela . In addition to the capital and operating cost benefits that would come with Cuprochlor-T over the concentration route , there is likely to be a sustainability benefit .
“ It ’ s only an indicative reference as each case is different , but you would expect the energy consumption associated with Cuprochlor-T leaching and SX-EW treatment to be less than half of the normal route of copper concentration and SX-EW ,” Muchnik said . In this respect , it is a favourable consideration for Antofagasta ’ s longterm carbon-neutral goals . www . antofagasta . co . uk

Innovative lithium battery locos at Onaping Depth

Clayton Equipment Ltd based in Burton-on- Trent , UK has sold and delivered five ( with an option for a sixth ) CB12.5 state of the art lithium-ion battery locos for Glencore ’ s Onaping Depth nickel-copper mine in Sudbury , which are notable as being the first Li-ion battery electric machines to be operational on site . These will operate on the main 1,200 m haulage level which was positioned there as that is at the top of the existing Craig Mine ore and waste pass system , so effectively utilising that system ’ s capacity .

Onaping Depth is set to start production in 2024 . The Onaping Depth mine will have a rock production capacity of 1.74 Mt / y which is waste and ore combined , of which some 1.4 Mt / y will be ore , constrained by the hoist capacity of 248 t / h , with the waste backfilled via an underground paste backfill plant .
Steve Gretton , Clayton Managing Director told IM : “ Glencore is not new to mining rail – we sold then Xstrata some 25 t battery locos going back about six years for the Fraser mine . So they are well used to rail underground and to Clayton products . Those machines were good solid units with the best electronic controls available at the time , but these locos for Onaping Depth are on another level , equipped with full WiFi , peer to peer communications and the latest Li-ion batteries plus a customised safety logic system .”
Clayton has also enabled wireless connection to remote driving stations at the discharge point and the loading point which is linked to the feed rate of the loading point . “ It is quite a sophisticated solution to their materials handling needs and has been designed in conjunction with the team at Glencore .”
Gretton said that when the mine gets its own network up and running ( wireless mesh or LTE ) the trains will use both that network to communicate with the overall mine control platform as well as the rail system ’ s own network controlling things at a train scale .
The trains will consist of two locos either end of an A train or B train – the A train being used for ore and waste ( 239 t maximum ), and B trains for personnel and materials . The A train will have 14 , 5.8 m 3 bottom discharge rail cars from Nordic Minesteel Technologies in North Bay ( one empty as an overspill ) and the maximum haulage distance will be 1.6 km . The battery capacity will be enough for 10 hours of operation during each shift with each loco ( two in each train ) having two 52 kW motors and 184 kWh of battery power .
The trains need to be rotated on a regular basis between being A and B trains as the A trains will take much more weight which means more battery power demand – this will even out the usage pattern for the battery packs & will allow them to last up to 15 years . It will not be the first Li-ion battery mining rail system but is certainly the most powerful ever built . The batteries were supplied by a Canadian manufacturer for combining with the locos shipped from the UK .
The locos arrived in Canada in late 2020 after testing in the UK and started working in May 2021 following certification , approvals , battery fitting and testing at Clayton ’ s Canadian agency facility , Variant Mining Technologies ( VMT ) in Sudbury , only half an hour from the mine . The locos went down the shaft in three pieces for final assembly underground .
The haulage level will include 12 track lines . The rail system itself will have its own WiFi network and RFID tagging to allow the locos to read speed limits based on what line they are going to , what type of train it is and what ’ s coming next , including applying autonomous braking using hydraulic disc brakes plus dynamic service brakes for operator use .
While there will be loco operators , he or she cannot override the set overspeed limits ; with 16 km / h set for personnel trains and 10 km / h for trains carrying any explosives . They cannot take the train where the safety logic does not allow
such as a fully laden ore train into the s
6 International Mining | AUGUST 2022