IM 2020 September 20 | Page 76

SHAFT SINKING The main component that needs to be tested will be the cutterhead and the pneumatic mucking system “because that rock is likely to be a lot more abrasive than the soft rock the SBR has been mucking”, Greinacher said. The SBC technology is likely to have the widest application in the shaft sinking industry, according to Greinacher, but he does not expect such technologies to replace drill and blast entirely. “Not each and every shaft is suitable for mechanised shaft sinking; some will be better suited to drill and blast operations,” he said. Therefore the company continues to pursue an automated drill and blast project for shaft sinking. Intended for both hard and softer rock, the plan is for the technology to enable mucking and lining in the shaft concurrently without any personnel at the face. The mucking system is likely to be based on an “excavator-type mucker”, Greinacher says, similar to the equipment used in other shaft sinking projects. COVID-19 and its work on the SBC technology might have pushed back the schedule for testing of this system, but Greinacher is confident of carrying out trials on this innovation in the first half of 2021. What about the SBS? Herrenknecht and Redpath Deilmann are not the only companies pushing a mechanised hard-rock cutting technology. Back in October, IM witnessed part of Master Drilling’s Shaft Boring System (SBS) concept in action at a location some 15 minutes’ drive outside of its Fochville, South Africa headquarters. This is where the company was testing out the main cutting mechanism of what could eventually be its 45-m long, 450-t SBS. The 15 in patented cutter heads of the machine were progressing through 320 MPa dolorite, cutting around 40-50 mm in displays for interested parties visiting the site. The SBS is billed as being able to cut and muck at the same time as shaft reinforcement, lining and other protective measures occur. It can work through hard rock from 200-400 MPa and sink shafts up to 1,500 m deep, advancing up to three times quicker than conventional sinking via drill and blast, according to the company. Three to five people are expected to be needed for its operation, none of whom are exposed to the face. The safety considerations also extend to the changing of the disc cutters, which can be removed and replaced from behind the cutting face. Like Master Drilling’s Mobile Tunnel Borer for horizontal development (previously working at Northam Platinum’s Eland PGM mine in the North West province of South Africa), the SBS will be commissioned off a launchpad. This will be constructed with minimal civils work and alleviate the need for a timely and expensive pre-sink phase, the company says. The front end of the machine (as it descends the shaft) is made up of the pilot cutting head – in a W-shape configuration – and gearbox. The pilot cutter head accounts for some 15% of the entire rock cutting, with the wider diameter reamer section that follows accounting for the remaining 85%. This first section can independently progress by 1.5 m when cutting is taking place in three separate 500 mm phases. The rest of the 45-m long machine catches up following this initial cutting, which is automated by a series of lasers to ensure the machine stays on the correct course and uses optimal force. This cutting station is followed by two shaft gripping stations for machine support within the shaft. Following this is an enlargement station – also equipped with cutters – that widens the pilot hole carried out by the pilot cutter head to the desired diameter, with Master Drilling saying this could range from 7.5 m to 11.5 m. Behind this is a main stage made up of eight separate levels. Here, personnel will be able to carry out the rock bolting, lining and other reinforcement measures. Personnel can probe drill ahead of cutting from one of these levels for geotechnical measurements, enabling them to anticipate the fracturability and hardness of rock, in addition to any potential water inflows. Personnel operating on this main stage are protected by a series of finger shields that, while guarding them from potential rockfalls, still allow for a 360° access to the shaft for services. A series of kibbles lowered by winches and transported on a conveyance on one of the stage levels bring the required shotcrete and materials to allow these concurrent tasks to take place. Kibbles will also help with the mucking process, with two 16 t capacity buckets transporting the Despite Master Drilling’s SBS hard-rock cutting mechanism being trialled in 320 MPa rock, no cutters were replaced over the three-month period it operated muck from the cut section to surface through a 2.1 m opening present in all stations. Master Drilling is relying on gravity to recover 85% of the volume of muck at the enlargement section, with the remaining 15% recovered using a vacuum and/or slurry system. The headgear to support these operations from surface will likely be around 35 m tall – small in comparison with other mechanised sinking setups – while the total power requirement comes in at around 10 MW, according to the company. Since IM’s visit almost a year ago, a lot has happened, but the core components remain the same. Originally targeting an advance rate of >500 mm/h during testing, Koos Jordaan, Executive Director of Master Drilling, confirmed back in March that the unit had hit close to 1 m/h instantaneous penetration during the latter trial stages. “In many cases we were fortunate,” Jordaan recently remarked on this feat. “I contribute it to many design concepts reviewed over the past two years and a radical approach to configuration at a high development risk.” The company tested the SBS cutting mechanism over a three-month period, excavating around 12 m of material in total at the site. Even with the stop-start nature of operations – with the SBS cutter generally only turning when potential SBS clients were in attendance – the repeatability was “reliable and impressive”, Jordaan told IM. Despite operating in 320 MPa rock, no cutters were replaced over this period. This is an important result considering the problems previously experienced with cutter wear in other mechanised hard-rock trials. 74 International Mining | SEPTEMBER 2020