IM 2020 September 20 | Page 74

SHAFT SINKING Herrenknecht. The steel liner rings were installed through the Blairmore aquifer to assist in the development of a composite steel and concrete watertight liner in both shafts. Since the project-specific design changes at Jansen required modifications to the SBRs, Herrenknecht, together with DMC, refined the technology over the long term. The result is the second generation of Herrenknecht SBR technology. As an example, the second generation SBR is equipped with an additional stabilisation level that allows the fixation of the SBR centre pipe on both ends. This ensures a stable transfer of the reaction forces from the cutting process to the shaft wall without movement of the machine – even with fluctuating excavation diameter of 8-11 m, as encountered at Jansen. In addition to an improved filter system, a new design of the PNM system was installed in the second-generation machine, which results in a higher degree of separation in the suction tank itself, allowing wet material and even water to be handled, Herrenknecht said. This next-generation machine also came with 600 kW of extra power compared with the first generation. Martin-Devid Herrenknecht, General Manager Mining at Herrenknecht, said: “The technical development of the second generation SBR is based on the lessons learnt from the Jansen project. “This pioneering approach is certainly a game changer for shaft sinking in soft and medium-hard rock, impacting the whole mining industry.” After the successful excavation at Jansen, another task was to be managed: the disassembly of the machines in the deep shafts. To remove the SBR from the shaft bottom, it was necessary to reduce the weight of the machine from 390 t to 340 t. This was achieved by stripping all components off the SBR that were in the excavation chamber. Both SBRs were safely extracted from the two shafts at the Jansen potash project in May 2019. Ahead of schedule Two second-generation SBRs were already in operation at IOOO Slavkaliy’s Nezhinskiy potash project, in Belarus, while the equipment dismantling at Jansen was ongoing. That project, using two SBRs to sink two shafts down to 750 m depth, with freezing required to 160 m depth, has broken Belarusian and European sinking records. Top maximum daily performance was around 7.4-7.5 m/d, while development rates of 144 m and 138 m (with sequential shaft lining) were achieved in the month of April 2020. Jochen Greinacher, Managing Director of Redpath Deilmann, Slavkaliy’s contractor and the company behind such SBR sinking rates, says that April record, in particular, was a big achievement. “That was shortly before we achieved the station level, so we had no opportunity to beat that record,” he told IM. “But that is almost 5 m/d on average, which is something to be proud of.” Despite there being issues during the shaft freezing section to 160 m depth, and the occurrence of weak rock, and water ingress in the next 160 or so metres of sinking, he was happy with overall performance. “When we talked last time (in July 2019), the SBRs were in the freeze section, and then we had, due to the weak rock and water ingress, geological problems below,” he said. “At this point, we had to leave the concept of simultaneous excavating and lining; we had to lower the forms into the cutting chamber and reduce the height of the forms from 5 m to 3.2 m which, of course, reduced the available cutting time and thus performance.” In that section – from around 160 m depth to 330 m depth, with the changed procedure and methodology – the best performance was achieved, according to Greinacher. “Not so much in terms of absolute metres per days, but in the respect that, even after departing from simultaneous excavating and lining, we achieved close to 4 m/d on average over a long period of time,” he said. The record April development numbers were achieved in salt rock-type conditions, Greinacher explained. “From 500 m down – when we had already reinstated excavating and lining at the same time – we were mainly in the rock salt and that is comparably simple; the sidewalls are stable, no water comes in and the rock has very homogeneous conditions,” he said. “That is where we then achieved the 144 m monthly figure.” It should not be forgotten, these latter records were achieved during COVID-19, when social In August 2018, two blind shafts at BHP’s Jansen were completed to depths of 975 and 1,005 m, respectively, using Herrenknecht’s SBR technology distancing was in place on site, fewer people were in the cage and masks were being worn. “It didn’t really impact production,” Greinacher said of such restrictions. “At the same time as all of this was happening the routine got better and fine tuning was taking place to improve performance. “I wouldn’t say COVID-19 had a negative impact on production.” Asked about current progress on the project, he said: “We are just in the final stages of lining the stations. We ended up carrying out the station excavation with a little roadheader (a Voest-Alpine (now Sandvik) AM-50), which wasn’t in the original plan, but performed very well.” The original plan was to drill and blast these stations, but with the border between Belarus and Russia closed due to COVID-19 restrictions and no domestic supplier of explosives in the country, the company instead used the available roadheader. “I think we have another month or so ahead to complete the reinforced concrete liner of the stations,” he told IM in mid-July. “Due to the fact we only had one roadheader, we completed the sinking in one shaft at a time, including the sump, and then backfilled it again with loose material, which you can get out quickly by using the PNM system of the SBR. On the other station, there is still the sump to sink and the loading pocket area to excavate.” The company then needs to equip the shaft and install and commission the skip hoisting system. After that, the lateral development work can start, probably early in 2021. Even with all this work ahead of it – and a slight delay to the original target of starting the shaft sinking in January 2019 – Redpath Deilmann is well ahead of schedule, Greinacher said. 72 International Mining | SEPTEMBER 2020