IM 2019 November 19 | Page 11

OPERATION FOCUS Outotec TankCells at Kyzyl which are used to produce both low and high carbon concentrate ended June 30, 2019. “Excellent results from Kyzyl drove our production growth while other operations delivered strong performances,” said Vitaly Nesis, Group CEO. The operation has continued to benefit from high-grade softer ore and has exceeded design specifications on throughput, grade and production. Half-year gold production came in at 159,500 oz of gold with 187,400 oz of gold produced in concentrate. The average concentrate recovery rate has increased to 87.8% despite low mass pulls achieved to improve transportation economics and attractiveness of concentrate for Chinese off-takers. Share of gold in low-carbon concentrate processed at the Amursk POX plant exceeded 50%. The processing plant is now running at a rate of 2 Mt/y – well above its nameplate capacity of 1.8 Mt/y. Recent performance tests have demonstrated that further improvement in throughput can be achieved with a $3 million investment in hydrocyclones and the concentrate filtering area. Open-pit mining has continued at a stable pace. A detailed technical study is under way to re-optimise the open pit under updated operational and economic assumptions with the results, including the updated Ore Reserves estimate, to be presented in Q4 2019. haul road maintenance. So far ore production and plant throughput (2 Mt/y instead of 1.8 Mt/y) have exceeded design numbers thanks to softer than expected ore, small high-grade ore pods and positive grade reconciliation near surface with group total cash costs (TCC) also lower than predicted at $407/oz in H1 2019. To maximise this positive performance Polymetal is now looking to deepen the open pit the plan for which along with the reserves update will be announced in Q4 2019. The mine has a truck fleet with 26 BELAZ 136 t 75139 trucks used to haul overburden, loaded by five Russian IZ-Kartez EKG 15M 15 m 3 electric rope shovels and nine Komatsu 91 t HD785 units used to haul the gold ore itself, loaded by five Komatsu hydraulic face shovels: three PC2000, plus smaller PC1250 and PC300 models. Ancillary equipment for waste and ore management includes a large fleet of 10 crawler dozers including Komatsu D375A-5 models. Kyzyl has a large maintenance shop to service its truck fleet. There are two truck maintenance bays dedicated to BELAZ, two for Komatsu and one for other OEMs. The hydraulic excavators for ore loading have their own maintenance facility but regular servicing is carried out in the pit itself, with the EKG machines serviced in-pit. A VIST Karier fleet management system is used. Polymetal carries out its own service work for lubricants/oils, tyres/wheels changeouts as well as welding steel wear plate to truck bodies with two contractors conducting more extensive maintenance for engines, system electronics, axles etc. There is also an in-house machining facility for certain spare parts such as hydraulic cylinders. Currently mainly Michelin radial tyres are used. The mine employs truck operators that have been trained at the technical college in Ust- Kamenogorsk, where there is also a truck simulator. Trainees then come to site for an internship period before becoming full time employees. The mine operates two 12 hour shifts with a total of two hours allocated to maintenance and breaks. Overall the mine has some 1,140 workers (Polymetal), not including contractors. The overall remote site management including catering, housekeeping, facilities management and support services is carried out by CAC Kazakhstan, part of the CIS International Group. Process plant design The process plant was designed in-house by Polymetal Engineering not by a third party engineering firm. The processing route (see box for summary) for Kyzyl’s highly carbonaceous preg-robbing sulphide includes an ex-pit primary crusher then a Outotec SAG mill for initial milling and screening using a bank of Metso inclined screens followed by a bank of flotation cells for carbon removal, then intermediate flotation followed by gravity Simplified flowsheet of Kyzyl plant Open-pit mining An open pit cut-off grade of 2 g/t was used in the pit design with average wall angle of 41-48 degrees and the pit walls monitored using a Leica slope stability radar. In bulk terms some 75,000 m 3 of material is mined per day with blasting conducted three to four times a week by a contractor. The blasthole fleet consists of a fleet of electric Epiroc PV271 Pit Vipers. Most of the waste is stockpiled but some 3% is used for NOVEMBER 2019 | International Mining 9