Pressure relief tee step by step operation The operation of the pressure relief tee is shown in the attached sequence: 1 Both nuts are undone 3 Joints shown as Victaulic, other joint types available Smooth consistent internal bore Fully welded construction Nut is retained by shoulder 5 2 Plug part is semi-captive Tool pass through slot Simple removal of polycarbonate windows by single bolt Conclusion Although there is a place in a paste pipeline for automated valves and cleanout tees it is proposed that this device fits a specialty niche between those two extremes and offers a superior pressure relief capability than cleanout tees or blasting tees, while doing so at a much lower cost than an automated valve. We believe that these devices should be installed at approximately every 300 m spacing in a paste backfill line to ensure that a safe and reliable depressurisation option is available throughout the pipeline. Smooth consistent internal bore Patented design Tool reversed Tool used to knock coupling from shoulder 6 4 Lift end of bar 7 Tool used as a lever to pull plug down Figure 1. Operation of the Pressure Relief Tee DIEMME ® FILTRATION FAST CYCLING FILTER PRESS GHT F The GHT F is a Diemme ® )LOWUDWLRQoOWHUSUHVVVSHFLoFDOO\GHYHORSHGIRUODUJHWKURXJKSXWKLJK oOWHUDELOLW\SURGXFWVVXFKDVPLQLQJFRQFHQWUDWHVDQGWDLOLQJV7KHHOHFWULFDOO\GULYHQPRYHPHQWRI WKHPRELOHKHDGHUDQGWKHUHVXOWLQJDFFRUGLRQVW\OHRSHQLQJRIWKHSODWHSDFNFRQVLGHUDEO\UHGXFHV WKHFDNHGLVFKDUJHWLPHDQGWKHHQWLUHRSHQLQJFORVLQJVHTXHQFHRIWKHoOWHU 7KHUHVXOWLVDIDVWF\FOLQJoOWHUSUHVVZKLFKDOORZVLQFUHDVHGSURGXFWLRQSHUXQLWDUHDRIWKHoOWHU www.aqseptence.com P2 International Mining | MARCH 2018 Supplement