IM 2017 April | Page 50

MINING PUMPS Impelling progress Paul Moore looks at pump market developments, from new models to refinements of existing models and technology additions he overall trend in hard rock mining to extract ever increasing tonnages of low grade ores, historically considered to be uneconomic, has led to the development of larger equipment from the mine face through the concentrator and on to tailings. FLSmidth Krebs Products Director, Brad Moralee, told IM: “The required development of larger pumps, though challenging, has not presented insurmountable difficulties. Along with these ever-increasing tonnages, reliability and efficiency is of paramount importance and will remain so for the foreseeable future.” T Saving by downsizing Sometimes increasing efficiency in a related process means an operation can install a smaller pump elsewhere and make resultant cost savings. In Australia, Kirkland Lake Gold’s Fosterville gold mine reduced its maintenance costs significantly using new cyclone liners. But even more interestingly, they reduced their annual mill pump operating costs by 40-50% as the new cyclone liners made it possible to install Krebs millMAX™ technology. The Fosterville gold mine is the largest producing gold mine in Victoria, Australia. It poured its one millionth ounce of gold back on January 7, 2016. This important milestone represented over 11 years of continuous operations since mining commenced in 2004. In 2016, Fosterville produced 151,755 oz; and daily mine throughput in 2016 was 1,900 t/d. Fosterville had originally operated with large sized pumps to handle the high recirculation load through the mill. This recirculating load was caused by oversized/worn cyclone spigots. Once the cyclone ceramic liners were installed the efficiency of the cyclones improved significantly - reducing 48 International Mining | APRIL 2017 recirculating load through the mill and mill pumps. Fosterville has four cyclones in operation and used to replace one apex per week to stagger the hours. The highest wearing component of the cyclones is the underflow apex. The rubber apexes had typically worn from a diameter of 82 mm when new to 105 mm after 672 h (four weeks) of operation. After the 4th apex (2,688 h) the cyclone was removed from service and was rebuilt with new liners by the maintenance personnel. Each rebuild cost approximately A$8,000 in materials and A$1,000 in labour, including the time to replace the apex liners. To reduce the significant maintenance cost Fosterville asked FLSmidth to replace the cyclone liners with FLSmidth Krebs ceramic lined cyclones. The FLSmidth Krebs ceramic lined cyclones have a much greater life with the underflow apex diameters wearing approximately 20 times slower compared to rubber. However, they are not allowed to increase to as large a diameter as The first FLSmidth Krebs millMAX10x8-24 mill discharge pump installation onsite at Fosterville Gold, which was given the go ahead after new cyclones success at the site and has since seen both mill discharge pumps replaced from competitor pumps to Krebs millMAX. From left to right: Adam Noble (FLSmidth Krebs Area Sales Manager), Kay Katov (Fosterville Gold Senior Metallurgist), Andrew Nash (Fosterville Gold Process Engineer) KSB says it has made a strong commitment to the oil sands industry in Alberta by establishing a service centre and parts warehouse the old rubber apexes. Instead the cyclones are removed from service after 8,760 h (one year) of service when the apex reaches 95 mm. The four cyclones are staggered to replace one per quarter. The ceramic lined cyclones are supplied to site as a complete assembled unit. The maintenance team can replace the whole unit and no longer have to commit time to replacing the liners. Changing cyclone liners improved Fosterville’s separation process in that this practice of replacing the worn apexes with new ones introduced a positive ledge where the new liner met the worn one above it, which interrupted the flow of slurry through the cyclone and rejected oversize material to the overflow. The effect of this could be observed in the bottom of the flotation cells which contained a lot of coarse material which inhibited the dart plug operation and accelerated the wear of the rotors and stators. The worn apexes also allowed excess fine particles to report to the underflow which increased the recirculating load and unnecessarily accelerated the wear of the mill components and discharge pumps. It also decreased the percentage of the underflow which could report to the flash flotation cell. The overflow p80 sizing is now less variable, but more noticeable is the significant reduction in coarse material in the flotation cells observed during shutdowns. Andrew Nash, Fosterville Gold Process Engineer states: “The benefit in this for Fosterville was overall reduced costs of operation and less wear to mill liners and mill process pumps due to the reduction of recirculating load. But even more interesting; the improved separation process allowed for smaller and far more efficient pumps to be installed.” The reduction in fines bypass to the underflow and the lower recirculating load has