Home Plate Update November 2020 | Page 16

2019 CONTINUED

October

Construction of the retractable-roof trusses was completed .

October 23

The first seat was installed at Globe Life Field , located on the main concourse behind home plate .

Nov . 18

Globe Life Field celebrated the “ Topping Out ” of the facility with the last piece of steel installed on the retractable roof .

December

The Rangers take batting practice at Globe Life Field for the first time .

December 6

The 5.5-acre retractable roof was closed for the first time .

December 17

Arlington City Council enters into public-private partnership over 30-year period to facilitate even more transformative development near ballpark , including a best-in-class hotel , new convention center , corporate office headquarters , mixeduse residential building , small business coworking and incubator space , and even more dining , retail , and entertainment options .

January

Installation began on the playing surface , a process that took one month to complete .

January 23

The first Globe Life Field sign was installed , located at the North Plaza entrance adjacent to Texas Live !

February 28

Installation of the artificial turf playing surface was completed .