Cost of Project
• Infrastructure ( Electrical , Sanitary , Shaping , Hole Relocation , Parking Lot , Safety Netting ) - $ 1,617,000
• Buildings ( Foundation / Framing , Electrical , Plumbing , Mechanicals , FF & E ) - $ 1,610,000
• Soft Costs ( Architecture , MEP , Permits ) - $ 120,250
• Simulators & Toptracer Technology - $ 419,000
• Total Project Costs - $ 3,766,250
8