GSCM 520 RANK Let's Do This /gscm520rank.com GSCM 520 RANK Let's Do This /gscm520rank.com | Página 16
9.
Question :
(TCO 3) In setting up a Kanban control system,
you need to determine the number of Kanban card sets needed. If the
expected demand during lead time is 25 per hour, the safety stock is
20% of the demand during lead time, the container size is five, and the
lead time to replenish an order is 5 hours, what is the number of
Kanban card sets needed?
10.
Question :
(TCO 3) To implement lean production
schedules, a firm would do which of the following?
===============================================
GSCM 520 Week 4 Case Study Toshibas Notebook
Computer Assembly Line
FOR MORE CLASSES VISIT
www.gscm520rank.com
Task
In a three-page paper, answer the following. Pg 199
·What is the daily capacity of the assembly-line design by the
engineers?
·When it is running at maximum capacity, what is the efficiency of the
line relative to its use of labor? Assume that the supporter is not
included in efficiency calculations?
·How should the line be redesigned to operate at the initial 250 units
per day target, assuming that no overtime will be used? What is the
efficiency of your new design?
·What other issues might Toshihiro consider when bringing a new
assembly line up to speed?
===============================================