9. Question : (TCO 3) In setting up a Kanban control system, you need to determine the number of Kanban card sets needed. If the expected demand during lead time is 25 per hour, the safety stock is 20% of the demand during lead time, the container size is five, and the lead time to replenish an order is 5 hours, what is the number of Kanban card sets needed? 10. Question : (TCO 3) To implement lean production schedules, a firm would do which of the following? =============================================== GSCM 520 Week 4 Case Study Toshibas Notebook Computer Assembly Line FOR MORE CLASSES VISIT www.gscm520rank.com Task In a three-page paper, answer the following. Pg 199 ·What is the daily capacity of the assembly-line design by the engineers? ·When it is running at maximum capacity, what is the efficiency of the line relative to its use of labor? Assume that the supporter is not included in efficiency calculations? ·How should the line be redesigned to operate at the initial 250 units per day target, assuming that no overtime will be used? What is the efficiency of your new design? ·What other issues might Toshihiro consider when bringing a new assembly line up to speed? ===============================================