the number of Kanban card sets needed. Your research shows that
the expected demand during lead time for a particular component is
1,200 per hour. You estimate the safety stock should be set at 5% of
the demand during lead time. The tote trays used as containers can
hold two units of stock and the lead time to replenish an order is 10
hours. Which of the following is the number of Kanban card sets
necessary to support this situation?
(Points : 10)
5,000
5,500
6,300
6,500
7,000
Question 9.9. (TCO 7) In a work center, machine A has a 10-minute
setup time per batch and a 2 minute per unit run time. Machine B
performs the identical function but has a setup time of 30 minutes
and a 1-minute run time per unit. The work center makes products
in batches ranging from one unit to 100 units. Assuming capacity is
not a limitation on either machine, on which batches should
machine B be used?
(Points : 10)
All batches should be run on machine B.
Batches of more than 20 units should be run on machine B.
Batches of fewer than 80 units should be run on machine B.
Batches with up to 50 units should be run on machine B
.
No batches should be run on machine B.
Question 10.10. (TCO 8) If annual demand is 6,125 units, annual
holding cost is $5 per unit, and setup cost per order is $50, which of
the following is the EOQ lot size?
(Points : 10)
350
247
23
185