SECTION 2 - Development Services Fees
Development Review Fees
|
Flat Fee |
Per Unit Fee |
Major Subdivision , Preliminary Plat |
$ 600 |
$ 10 / lot |
Major Subdivision , Preliminary Plat Modification Admin . |
$ 150 |
$ 5 / lot |
Site Plan Residential |
$ 750 |
$ 10 / unit |
Site Plan Non-Residential |
$ 750 |
$ 10 / acre |
Site Plan Modification – Admin . ( Residential ) |
$ 150 |
$ 5 / unit |
Site Plan Modification – Admin . ( Non Residential ) |
$ 150 |
$ 5 / acre |
Planned Development ( must file a Conditional Re-zoning application ) |
$ 750 |
$ 10 / acre |
Special Use Permit ( must also file a site plan , major subdivision or building reuse zoning |
$ 500 |
|
compliance application ) |
||
Temporary Use Permit |
$ 25 |
Plan Review Re-Submittal ( 4th or more – each re-submittal ) |
50 % of Original Fee |
|
Planning Site Inspection Fees |
Flat Fee |
Per Unit Fee |
Site Inspection – Single Family or Townhome Lot |
$ 50 |
|
Site Inspection – Other ( flat fee includes 1 st acre ) |
$ 75 |
$ 5 / add ' l acre |
Site Re-Inspection |
50 % of Original Fee |
|
Final Plat Petition Fees |
Flat Fee |
Per Unit Fee |
Exemption , Recombination or Easement Plat |
$ 100 |
|
Final Plat - Major |
$ 300 |
$ 5 / lot |
Final Plat - Minor |
$ 200 |
|
Zoning Compliance Permit Fees |
Flat Fee |
Per Unit Fee |
Accessory Structure |
$ 50 |
|
Building Reuse-General ( all other required zoning compliance ) |
$ 150 |
|
Fence |
$ 35 |
|
Home Occupation |
$ 35 |
|
Sign Fees |
Flat Fee |
Per Unit Fee |
Sign Permit ( per sign ) |
$ 75 |
|
Temporary Sign Permit ( per sign ) |
$ 35 |
|
Temporary Off-Premise Subdivision Sign Permit |
$ 100 |
|
Temporary On-Premise Construction Identification Signs |
$ 100 |
|
Other Fees |
Flat Fee |
Per Unit Fee |
Annexation Petition – Voluntary |
$ 200 |
|
Re-zoning , General or Conditional Map Amendment |
$ 500 |
$ 10 / acre |
Zoning Verification Letter |
$ 150 |
|
Administrative Zoning Interpretation |
$ 150 |
|
Board of Adjustment Application ( Variance , Special Exception , Administrative Appeal ) |
$ 500 |
|
UDO Text Amendment |
$ 500 |
|
Petition to Close Street |
$ 450 |
|
Comprehensive Growth Plan Amendment |
$ 500 |
|
Engineering Fees |
Flat Fee |
Per Unit Fee |
Initial Construction Drawing Fee ( Includes 2 reviews and 1 signature submittal ) |
$ 600 |
$ 10 / lot |
Subsequent Construction Drawing Fee ( per each additional review ) |
$ 300 |
|
Street Inspections |
$ 1.50 / linear ft |
|
Sidewalk / Greenway Inspections |
$ 1.50 / linear ft |
|
Curb and Gutter Inspections |
$ 1.50 / linear ft |
|
Curb Cut Inspections |
$ 100 |
|
Driveway Permit |
$ 100 |
|
Major Right of Way Encroachment |
$ 200 |